Atwell Island West Solar
A 20 MW solar power plant in Tulare, California, owned by Consolidated Edison Development Inc., commissioned in 2015.
Facility nameplate · EIA Plant ID 59414Solar
Nameplate capacity
20 MW
Primary fuel
Solar
Commissioned
2015
Time in queue (2009→2015)
6.1 yrs
Owner
Consolidated Edison Development Inc.
Location
Tulare, California
Coordinates
Generation (2024)
45.4 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
This facility was matched to a CAISO interconnection request (LBNL Queued Up): queued 2009, commercial operation 2015 — 6.1 years in the queue. See the CAISO queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2015 | 32.2 | |
| 2016 | 57 | |
| 2017 | 55.7 | |
| 2018 | 55.4 | |
| 2019 | 53.2 | |
| 2020 | 51.7 | |
| 2021 | 37 | |
| 2022 | 44.1 | |
| 2023 | 46.5 | |
| 2024 | 45.4 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| White River Solar | Solar | 20 MW | ~6 km |
| Alpaugh 50 | Solar | 50 MW | ~10 km |
| Alpaugh North | Solar | 20 MW | ~10 km |
| Atwell Island | Solar | 20.2 MW | ~10 km |
| Avalon Dairy | Solar | 3.1 MW | ~11 km |
| Delano Land 1 | Solar | 1 MW | ~12 km |
See all solar plants in California or browse all plants in California.