Atwell Island West Solar

A 20 MW solar power plant in Tulare, California, owned by Consolidated Edison Development Inc., commissioned in 2015.

Facility nameplate · EIA Plant ID 59414Solar
Nameplate capacity
20 MW
Primary fuel
Solar
Commissioned
2015
Time in queue (2009→2015)
6.1 yrs
Location
Tulare, California
Generation (2024)
45.4 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a CAISO interconnection request (LBNL Queued Up): queued 2009, commercial operation 2015 — 6.1 years in the queue. See the CAISO queue or typical durations.

Location

Map of the United States showing the location of Atwell Island West Solar

Tulare, California · 35.815, -119.4597

Reported annual generation

YearGWh
201532.2
201657
201755.7
201855.4
201953.2
202051.7
202137
202244.1
202346.5
202445.4

Nearby power plants

PlantFuelCapacityDistance
White River SolarSolar20 MW~6 km
Alpaugh 50Solar50 MW~10 km
Alpaugh NorthSolar20 MW~10 km
Atwell IslandSolar20.2 MW~10 km
Avalon DairySolar3.1 MW~11 km
Delano Land 1Solar1 MW~12 km

See all solar plants in California or browse all plants in California.