Forward-looking · interconnection queue
U.S. interconnection queue
9,168 proposed generation and storage projects — 8,500 active and 668 suspended — are waiting to connect to the U.S. grid, representing 1881.24 GW of requested capacity across 48 states and nine ISO/RTO and non-ISO regions. Solar + Battery makes up the largest share at 456.42 GW.
9,168
Proposed projects
1881.24 GW
Requested capacity
48
States
2027
Median planned online year
Requested capacity is the primary component of each request (LBNL mw_1). LBNL's headline figure of 2,061 GW additionally counts the storage component of hybrid projects; the two are never mixed here.
Requested capacity by resource type
Solar + Battery 24.3%Solar 22.9%Battery 22.2%Gas 13.8%Wind 11.7%Other 2.4%Offshore Wind 1.3%Nuclear 0.6%
By region
By state
Alabama91 · 14.38 GWArizona281 · 91.80 GWArkansas157 · 35.42 GWCalifornia463 · 131.82 GWColorado206 · 41.77 GWConnecticut7 · 678.2 MWDelaware16 · 874.4 MWFlorida251 · 24.34 GWGeorgia204 · 46.50 GWIdaho83 · 20.97 GWIllinois423 · 74.63 GWIndiana300 · 59.60 GWIowa123 · 23.94 GWKansas140 · 32.57 GWKentucky134 · 21.50 GWLouisiana140 · 37.59 GWMaine16 · 1.03 GWMaryland57 · 5.94 GWMassachusetts35 · 11.21 GWMichigan302 · 58.64 GWMinnesota153 · 28.46 GWMississippi93 · 17.04 GWMissouri124 · 29.65 GWMontana62 · 15.37 GWNebraska85 · 16.53 GWNevada248 · 73.19 GWNew Hampshire3 · 125 MWNew Jersey71 · 15.96 GWNew Mexico159 · 32.23 GWNew York187 · 25.71 GWNorth Carolina182 · 20.89 GWNorth Dakota62 · 14.50 GWOhio183 · 19.75 GWOklahoma240 · 52.47 GWOregon323 · 85.85 GWPennsylvania231 · 12.49 GWRhode Island3 · 982.2 MWSouth Carolina195 · 19.91 GWSouth Dakota48 · 9.63 GWTennessee53 · 13.80 GWTexas2,090 · 476.54 GWUtah153 · 29.64 GWVermont5 · 128.6 MWVirginia287 · 30.29 GWWashington207 · 43.33 GWWest Virginia41 · 6.90 GWWisconsin117 · 26.56 GWWyoming80 · 18.53 GW
Largest proposed projects
| Type | ||||
|---|---|---|---|---|
| Schahfer CCGTs E0042 | Gas | 2.74 GW | 2025 | 2028 |
| ATLAS COMPLEX 1402 | Solar + Battery | 2.25 GW | 2017 | 2026 |
| Queue J3996 J3996 | Gas | 2.22 GW | 2025 | 2030 |
| Queue AI2-431 AI2-431 | Offshore Wind | 2.14 GW | 2023 | 2030 |
| Queue AI1-001 AI1-001 | Offshore Wind | 2.10 GW | 2022 | 2029 |
| CPV Shay, LLC project AG2-582 | Gas | 2.10 GW | 2025 | 2026 |
| JOVE SOLAR 2023 | Solar + Battery | 2.04 GW | 2021 | 2030 |
| Queue Q255 Q255 | Solar + Battery | 2.00 GW | 2017 | 2021 |
| Smarr CC GI-193 | Gas | 2.00 GW | 2024 | 2028 |
| Queue G0822 G0822 | Solar + Battery | 2.00 GW | 2022 | 2026 |
| Queue 489 489 | Gas | 1.69 GW | 2021 | 2026 |
| Prairie Ridge (Gas - CC) 30INR0071 | Gas | 1.66 GW | 2025 | 2032 |
| Queue Q92 Q92 | Solar + Battery | 1.65 GW | 2022 | 2025 |
| Sawtooth DevCo, LLC projectsusp. 659 | Solar + Battery | 1.65 GW | 2022 | 2027 |
| Sawtooth DevCo, LLC projectsusp. 660 | Solar + Battery | 1.65 GW | 2022 | 2027 |
| Franklin Farms E0014 | Gas | 1.64 GW | 2025 | 2028 |
| Richland Parish generators E0043 | Gas | 1.64 GW | 2025 | 2028 |
| Richland Parish generators E0044 | Gas | 1.64 GW | 2025 | 2028 |
| Queue 977726 977726 | Gas | 1.62 GW | 2025 | — |
| Queue 628 628 | Gas | 1.60 GW | 2024 | 2030 |
| Queue 483 483 | Gas | 1.60 GW | 2021 | 2025 |
| Queue 620 620 | Gas | 1.60 GW | 2024 | 2031 |
| Hecate Energy Orem Wind 27INR0061 | Wind | 1.54 GW | 2023 | 2030 |
| Queue J3999 J3999 | Gas | 1.54 GW | 2025 | 2030 |
| Aegle Power 27INR0084 | Gas | 1.54 GW | 2024 | 2027 |
Showing the 25 largest of 9,168 projects by requested capacity.
Queue insights & trends
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025). Read the queue insights.