Buckeye Wind Energy Center

A 200.5 MW wind power plant in Ellis, Kansas, owned by Invenergy Services LLC, commissioned in 2015.

Facility nameplate · EIA Plant ID 58767Wind
Nameplate capacity
200.5 MW
Primary fuel
Wind
Commissioned
2015
Time in queue (2008→2015)
7.3 yrs
Location
Ellis, Kansas
Generation (2024)
712.2 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1

This facility was matched to a SPP interconnection request (LBNL Queued Up): queued 2008, commercial operation 2015 — 7.3 years in the queue. See the SPP queue or typical durations.

Location

Map of the United States showing the location of Buckeye Wind Energy Center

Ellis, Kansas · 39.0039, -99.4142

Reported annual generation

YearGWh
2015278.9
2016820
2017794
2018759
2019806.9
2020821.6
2021748.6
2022789.6
2023743.7
2024712.2

Nearby power plants

PlantFuelCapacityDistance
Goodman Energy CenterNatural Gas103.5 MW~9 km
Fort Hays State University Wind FarmWind4 MW~14 km
Cedar Bluff Wind, LLCWind198.6 MW~44 km
StocktonNatural Gas8.6 MW~49 km
Russell DowntownNatural Gas15.7 MW~50 km
Russell Energy CenterNatural Gas15 MW~51 km

See all wind plants in Kansas or browse all plants in Kansas.