CED Centerville Wind
A 7.9 MW wind power plant in Appanoose, Iowa, owned by Consolidated Edison Development Inc., commissioned in 2021.
Facility nameplate · EIA Plant ID 64178Wind
Nameplate capacity
7.9 MW
Primary fuel
Wind
Commissioned
2021
Owner
Consolidated Edison Development Inc.
Location
Appanoose, Iowa
Coordinates
Generation (2024)
26.6 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2021 | 1.2 | |
| 2022 | 13.4 | |
| 2023 | 25.8 | |
| 2024 | 26.6 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Unionville City of | Oil | 8.7 MW | ~29 km |
| Unionville | Oil | 53.2 MW | ~31 km |
| Bloomfield Municipal Utilities Solar | Solar | 1.6 MW | ~34 km |
| Bloomfield | Natural Gas | 8.5 MW | ~36 km |
| High Prairie Wind Farm | Wind | 400 MW | ~44 km |
| Ottumwa | Coal | 725.9 MW | ~49 km |