CED Ducor 2
A 20 MW solar power plant in Tulare, California, owned by Consolidated Edison Development Inc., commissioned in 2016.
Facility nameplate · EIA Plant ID 60079Solar
Nameplate capacity
20 MW
Primary fuel
Solar
Commissioned
2016
Owner
Consolidated Edison Development Inc.
Location
Tulare, California
Coordinates
Generation (2024)
52.2 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2016 | 2 | |
| 2017 | 53.3 | |
| 2018 | 52.3 | |
| 2019 | 46.4 | |
| 2020 | 50.4 | |
| 2021 | 48.2 | |
| 2022 | 46.6 | |
| 2023 | 47.2 | |
| 2024 | 52.2 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| CED Ducor 3 | Solar | 15 MW | ~1 km |
| CED Ducor 1 | Solar | 20 MW | ~1 km |
| Nicolis Solar PV Plant | Solar | 20 MW | ~1 km |
| Tropico Solar PV Plant | Solar | 14 MW | ~2 km |
| Bottleneck Energy Storage | Storage | 80 MW | ~2 km |
| Luciana | Solar | 55.8 MW | ~2 km |
See all solar plants in California or browse all plants in California.