Cimarron Solar Facility

A 30.6 MW solar power plant in Colfax, New Mexico, owned by Southern Power Co, commissioned in 2010.

Facility nameplate · EIA Plant ID 57243Solar
Nameplate capacity
30.6 MW
Primary fuel
Solar
Commissioned
2010
Time in queue (2008→2010)
2.3 yrs
Location
Colfax, New Mexico
Generation (2024)
44.6 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a Non-ISO West interconnection request (LBNL Queued Up): queued 2008, commercial operation 2010 — 2.3 years in the queue. See the West queue or typical durations.

Location

Map of the United States showing the location of Cimarron Solar Facility

Colfax, New Mexico · 36.4681, -104.6357

Reported annual generation

YearGWh
201560.8
201663.7
201761
201863.3
201961.7
202062.5
202163.3
202260.7
202357
202444.6

Nearby power plants

PlantFuelCapacityDistance
Springer Solar 1Solar1 MW~9 km
Angel Fire Energy FacilitySolar11.2 MW~58 km
Syncarpha Eagle NestSolar1 MW~58 km
Trinidad (CO)Oil9.2 MW~80 km
Taos Mesa Energy Facility HybridSolar27.5 MW~88 km
Kit CarsonSolar1.3 MW~91 km