Cottonwood Wind Energy Center
A 89.7 MW wind power plant in Webster, Nebraska, owned by Cottonwood Wind Project, commissioned in 2017.
Facility nameplate · EIA Plant ID 61407Wind
Nameplate capacity
89.7 MW
Primary fuel
Wind
Commissioned
2017
Time in queue (2008→2017)
9 yrs
Owner
Cottonwood Wind Project
Location
Webster, Nebraska
Coordinates
Generation (2024)
410.6 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
This facility was matched to a SPP interconnection request (LBNL Queued Up): queued 2008, commercial operation 2017 — 9 years in the queue. See the SPP queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2017 | 68.9 | |
| 2018 | 411.7 | |
| 2019 | 423.8 | |
| 2020 | 432.6 | |
| 2021 | 412.7 | |
| 2022 | 437.9 | |
| 2023 | 410 | |
| 2024 | 410.6 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Little Blue Wind Project, LLC | Wind | 250.7 MW | ~5 km |
| City Light & Water | Oil | 1.3 MW | ~10 km |
| Red Cloud | Oil | 5.7 MW | ~18 km |
| Campbell Village | Oil | 1 MW | ~28 km |
| CCC Hastings Wind Turbine | Wind | 1.7 MW | ~37 km |
| Don Henry | Natural Gas | 22 MW | ~38 km |
See all wind plants in Nebraska or browse all plants in Nebraska.