Crafton Hills College Solar Farm

A 1.3 MW solar power plant in San Bernardino, California, owned by San Bernardino Comm College Dist, commissioned in 2012, retired in 2023.

Facility nameplate · EIA Plant ID 58170Retired 2023Solar
Nameplate capacity
1.3 MW
Primary fuel
Solar
Commissioned
2012
Owner
San Bernardino Comm College Dist
Location
San Bernardino, California
Generation (2023)
0 GWh
Status
Retired
Retired
2023
Technology
Solar Photovoltaic
Units
1

Reported annual generation

YearGWh
20152.1
20161.8
2017-0.4
20180.8
20191.5
20201.4
20211.1
20220.1
20230

Nearby power plants

PlantFuelCapacityDistance
Energy CenterNatural Gas0.9 MW~6 km
Santa Ana 3Hydroelectric3.1 MW~7 km
Mill Creek 3Hydroelectric3 MW~7 km
Redlands Community HospitalNatural Gas1.1 MW~10 km
Chambers 4 - Redland LGB4Solar1.9 MW~10 km
Santa Ana 1Hydroelectric3.2 MW~12 km