East Fork Wind Project, LLC
A 195.8 MW wind power plant in Thomas, Kansas, owned by Engie North America, commissioned in 2020.
Facility nameplate · EIA Plant ID 62220Wind
Nameplate capacity
195.8 MW
Primary fuel
Wind
Commissioned
2020
Time in queue (2015→2020)
4.5 yrs
Owner
Engie North America
Location
Thomas, Kansas
Coordinates
Generation (2024)
725 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
This facility was matched to a SPP interconnection request (LBNL Queued Up): queued 2015, commercial operation 2020 — 4.5 years in the queue. See the SPP queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2020 | 600.3 | |
| 2021 | 723.3 | |
| 2022 | 815.8 | |
| 2023 | 738.8 | |
| 2024 | 725 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Solomon Forks Wind Project, LLC | Wind | 275.6 MW | ~0 km |
| Colby City of | Oil | 20.7 MW | ~10 km |
| Colby | Natural Gas | 16 MW | ~11 km |
| Midwest Energy Community Solar Array | Solar | 1 MW | ~12 km |
| Western Plains Wind | Wind | 2.7 MW | ~36 km |
| Goodland | Natural Gas | 18.7 MW | ~54 km |
See all wind plants in Kansas or browse all plants in Kansas.