Ganado Solar
A 221 MW solar power plant in Jackson, Texas, owned by Enel Green Power NA, Inc., commissioned in 2023.
Facility nameplate · EIA Plant ID 67284Solar
Nameplate capacity
221 MW
Primary fuel
Solar
Commissioned
2023
Location
Jackson, Texas
Coordinates
Generation (2024)
325.5 GWh
Other fuels
Storage
Status
Operating
Technology
Solar Photovoltaic
Units
2
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2023 | 65.6 | |
| 2024 | 325.5 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Aktina Solar | Solar | 500 MW | ~25 km |
| Red Tailed Hawk Solar LLC | Solar | 350 MW | ~38 km |
| Pavlov | Storage | 9.9 MW | ~41 km |
| Formosa Utility Venture Ltd | Natural Gas | 933.4 MW | ~46 km |
| Tres Bahias | Solar | 196.3 MW | ~47 km |
| Colorado Bend Energy Center | Natural Gas | 654.1 MW | ~49 km |
See all solar plants in Texas or browse all plants in Texas.