Giffen Solar Park
A 20 MW solar power plant in Fresno, California, owned by Giffen Solar Park, LLC, commissioned in 2017.
Facility nameplate · EIA Plant ID 59522Solar
Nameplate capacity
20 MW
Primary fuel
Solar
Commissioned
2017
Time in queue (2011→2017)
6.2 yrs
Owner
Giffen Solar Park, LLC
Location
Fresno, California
Coordinates
Generation (2024)
19.3 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
This facility was matched to a CAISO interconnection request (LBNL Queued Up): queued 2011, commercial operation 2017 — 6.2 years in the queue. See the CAISO queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2017 | 29.1 | |
| 2018 | 37 | |
| 2019 | 31.8 | |
| 2020 | 30.1 | |
| 2021 | 30.8 | |
| 2022 | 28.1 | |
| 2023 | 21.9 | |
| 2024 | 19.3 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Giffen | Solar | 10 MW | ~2 km |
| Aspiration G | Solar | 9 MW | ~3 km |
| Great Valley Solar Portfolio Holdings, L | Solar | 202.5 MW | ~7 km |
| Scarlet Solar (CA) | Solar | 240 MW | ~7 km |
| RE Adams East, LLC | Solar | 19 MW | ~8 km |
| Scarlet II Hybrid | Solar | 350 MW | ~8 km |