Goal Line LP

A 51.4 MW natural gas power plant in San Diego, California, owned by Goal Line LP, commissioned in 1994.

Facility nameplate · EIA Plant ID 54749Natural Gas
Nameplate capacity
51.4 MW
Primary fuel
Natural Gas
Commissioned
1994
Owner
Goal Line LP
Location
San Diego, California
Generation (2024)
11.4 GWh
Status
Operating
Technology
Natural Gas Fired Combined Cycle
Units
2

Reported annual generation

YearGWh
201522.8
201623
201722.3
201818.1
20198.5
202018.7
202117.4
202210.8
202313.6
202411.4