Gold Meadow Farms
A 16.2 MW solar power plant in Kent, Rhode Island, owned by Captona Lippitt Ave Cranston LLC, commissioned in 2019.
Facility nameplate · EIA Plant ID 64108Solar
Nameplate capacity
16.2 MW
Primary fuel
Solar
Commissioned
2019
Owner
Captona Lippitt Ave Cranston LLC
Location
Kent, Rhode Island
Coordinates
Generation (2024)
28 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2020 | 29.3 | |
| 2021 | 27.9 | |
| 2022 | 29.4 | |
| 2023 | 27.5 | |
| 2024 | 28 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Hope Farm Solar, LLC | Solar | 10 MW | ~1 km |
| ISM Solar Cranston CSG | Solar | 3.1 MW | ~5 km |
| Central Power Plant | Natural Gas | 11 MW | ~6 km |
| WED Plainfield III, LLC | Wind | 3 MW | ~7 km |
| Kilvert | Solar | 4.7 MW | ~7 km |
| WED Plainfield II, LLC | Wind | 3 MW | ~7 km |