Hancock Creek Hydroelectric Project
A 6 MW hydroelectric power plant in King, Washington, owned by PUD No 1 of Snohomish County, commissioned in 2018.
Facility nameplate · EIA Plant ID 60517Hydroelectric
Nameplate capacity
6 MW
Primary fuel
Hydroelectric
Commissioned
2018
Owner
PUD No 1 of Snohomish County
Location
King, Washington
Coordinates
Generation (2024)
23 GWh
Status
Operating
Technology
Conventional Hydroelectric
Units
1
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2017 | 0 | |
| 2018 | 13 | |
| 2019 | 10 | |
| 2020 | 21.6 | |
| 2021 | 19.7 | |
| 2022 | 4.2 | |
| 2023 | 16.6 | |
| 2024 | 23 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Black Creek | Hydroelectric | 3.7 MW | ~3 km |
| Calligan Creek Hydroelectric Project | Hydroelectric | 6 MW | ~3 km |
| Snoqualmie | Hydroelectric | 12.8 MW | ~12 km |
| Snoqualmie 2 | Hydroelectric | 38.7 MW | ~12 km |
| Twin Falls Hydro | Hydroelectric | 24 MW | ~14 km |
| Weeks Falls | Hydroelectric | 4.3 MW | ~16 km |