Henrietta Solar Project
A 102 MW solar power plant in Kings, California, owned by Southern Power Co, commissioned in 2016.
Facility nameplate · EIA Plant ID 58975Solar
Nameplate capacity
102 MW
Primary fuel
Solar
Commissioned
2016
Time in queue (2010→2016)
6.5 yrs
Owner
Southern Power Co
Location
Kings, California
Coordinates
Generation (2024)
218 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
This facility was matched to a CAISO interconnection request (LBNL Queued Up): queued 2010, commercial operation 2016 — 6.5 years in the queue. See the CAISO queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2016 | 132.1 | |
| 2017 | 250.1 | |
| 2018 | 254.4 | |
| 2019 | 236.4 | |
| 2020 | 241.3 | |
| 2021 | 240.3 | |
| 2022 | 229.6 | |
| 2023 | 234.2 | |
| 2024 | 218 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Java Solar, LLC | Solar | 13.5 MW | ~2 km |
| RE Kansas South LLC | Solar | 20 MW | ~3 km |
| RE Kansas Solar, LLC | Solar | 20 MW | ~4 km |
| Lemoore 1 | Solar | 1.5 MW | ~4 km |
| Kings CSG 3 LLC Community Solar | Solar | 3 MW | ~8 km |
| Slate Hybrid | Solar | 440.3 MW | ~8 km |
See all solar plants in California or browse all plants in California.