Ida Grove II

A 201 MW wind power plant in Ida, Iowa, owned by MidAmerican Energy Co, commissioned in 2019.

Facility nameplate · EIA Plant ID 62795Wind
Nameplate capacity
201 MW
Primary fuel
Wind
Commissioned
2019
Time in queue (2014→2019)
4.9 yrs
Location
Ida, Iowa
Generation (2024)
734.5 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1

This facility was matched to a MISO interconnection request (LBNL Queued Up): queued 2014, commercial operation 2019 — 4.9 years in the queue. See the MISO queue or typical durations.

Location

Map of the United States showing the location of Ida Grove II

Ida, Iowa · 42.3269, -95.4588

Reported annual generation

YearGWh
201924.1
2020754.2
2021796.6
2022858.8
2023647.2
2024734.5

Nearby power plants

PlantFuelCapacityDistance
Ida Grove WindWind301.1 MW~4 km
New Harvest Wind Project LLCWind100 MW~19 km
Richland (IA)Wind130.9 MW~20 km
IntrepidWind175.5 MW~27 km
West ReceivingOil1.8 MW~35 km
Victory Wind FarmWind105 MW~36 km

See all wind plants in Iowa or browse all plants in Iowa.