IGS AKC1

A 3.8 MW solar power plant in Summit, Ohio, owned by Greenbacker Renewable Energy Corporation, commissioned in 2023.

Facility nameplate · EIA Plant ID 65985Solar
Nameplate capacity
3.8 MW
Primary fuel
Solar
Commissioned
2023
Owner
Greenbacker Renewable Energy Corporation
Location
Summit, Ohio
Generation (2024)
4.5 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

Reported annual generation

YearGWh
20232.3
20244.5

Nearby power plants

PlantFuelCapacityDistance
Akron WRFBiomass1.8 MW~12 km
Wadsworth IPS RTO BTMOil10.8 MW~13 km
Cuyahoga Falls 1Oil14.4 MW~14 km
Wadsworth HBS RTO BTMOil10.8 MW~14 km
DG AMP Rittman RdSolar2.6 MW~15 km
DG AMP 1048 WadsworthSolar6.3 MW~16 km