A 3 MW wind power plant in Baker, Oregon, owned by Lime Wind LLC, commissioned in 2011.

Facility nameplate · EIA Plant ID 57803Wind
Nameplate capacity
3 MW
Primary fuel
Wind
Commissioned
2011
Time in queue (2008→2011)
3.7 yrs
Owner
Lime Wind LLC
Location
Baker, Oregon
Generation (2024)
5.3 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1

This facility was matched to a Non-ISO West interconnection request (LBNL Queued Up): queued 2008, commercial operation 2011 — 3.7 years in the queue. See the West queue or typical durations.

Location

Map of the United States showing the location of Lime Wind

Baker, Oregon · 44.3969, -117.2719

Reported annual generation

YearGWh
20156.1
20165.9
20175.5
20186.1
20195.9
20205.3
20216.3
20225.5
20234.8
20245.3

Nearby power plants

PlantFuelCapacityDistance
Willow Spring Windfarm (Burnt River)Wind10 MW~2 km
Prospector Windfarm (Burnt River)Wind10 MW~3 km
Jett Creek Windfarm (Burnt River)Wind10 MW~3 km
Durbin Creek Windfarm (Burnt River)Wind10 MW~6 km
Benson Creek Windfarm (Burnt River)Wind10 MW~7 km