MA Blackstone
A 7.2 MW solar power plant in Worcester, Massachusetts, owned by Catalyze Blackstone 83 Federal Street Microgrid, LLC, commissioned in 2022.
Facility nameplate · EIA Plant ID 66474Solar
Nameplate capacity
7.2 MW
Primary fuel
Solar
Commissioned
2022
Owner
Catalyze Blackstone 83 Federal Street Microgrid, LLC
Location
Worcester, Massachusetts
Coordinates
Generation (2024)
3.7 GWh
Other fuels
Storage
Status
Operating
Technology
Solar Photovoltaic
Units
2
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2022 | 2 | |
| 2023 | 4.5 | |
| 2024 | 3.7 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Blackstone/Tupperware | Hydroelectric | 1.6 MW | ~2 km |
| Thundermist Hydro | Hydroelectric | 1.2 MW | ~3 km |
| ANP Blackstone Energy Project | Natural Gas | 578 MW | ~4 km |
| Hurteau Solar Project Hybrid | Solar | 3.3 MW | ~5 km |
| Palombo B Solar, LLC CSG | Solar | 1 MW | ~6 km |
| Palombo Solar, LLC CSG | Solar | 2 MW | ~6 km |