A 280 MW solar power plant in San Bernardino, California, owned by Mojave Solar LLC, commissioned in 2014.

Facility nameplate · EIA Plant ID 57331Solar
Nameplate capacity
280 MW
Primary fuel
Solar
Commissioned
2014
Time in queue (2006→2014)
8.3 yrs
Owner
Mojave Solar LLC
Location
San Bernardino, California
Generation (2024)
629.1 GWh
Status
Operating
Technology
Solar Thermal without Energy Storage
Units
2

This facility was matched to a CAISO interconnection request (LBNL Queued Up): queued 2006, commercial operation 2014 — 8.3 years in the queue. See the CAISO queue or typical durations.

Location

Map of the United States showing the location of Mojave Solar Project

San Bernardino, California · 35.0177, -117.3391

Reported annual generation

YearGWh
2015503.6
2016624.9
2017594
2018605.2
2019514.5
2020558.4
2021588
2022595.7
2023612.4
2024629.1

Nearby power plants

PlantFuelCapacityDistance
Lockhart Solar PV, LLCSolar100.4 MW~2 km
Lockhart ESS, LLCStorage45 MW~2 km
Lockhart Solar PV IISolar84.4 MW~3 km
Resurgence SolarSolar165 MW~19 km
Resurgence Solar IISolar88 MW~19 km
Madelyn Solar, LLCSolar1 MW~28 km