Moorhead Wind Turbine
A 1.4 MW wind power plant in Clay, Minnesota, owned by City of Moorhead - (MN), commissioned in 1999.
Facility nameplate · EIA Plant ID 7855Wind
Nameplate capacity
1.4 MW
Primary fuel
Wind
Commissioned
1999
Owner
City of Moorhead - (MN)
Location
Clay, Minnesota
Coordinates
Generation (2024)
1.2 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
2
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2015 | 2.5 | |
| 2016 | 1.4 | |
| 2017 | 1.9 | |
| 2018 | 1.5 | |
| 2019 | 1.7 | |
| 2020 | 2.2 | |
| 2021 | 1.4 | |
| 2022 | 0.4 | |
| 2023 | -10.3 | |
| 2024 | 1.2 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| American Crystal Sugar Moorhead | Coal | 5 MW | ~2 km |
| Centennial Generating Station | Oil | 11.5 MW | ~3 km |
| USS Buckaroo Solar LLC CSG | Solar | 1 MW | ~20 km |
| USS KVPV Solar LLC CSG | Solar | 1 MW | ~20 km |
| Spring Prairie Solar LLC CSG | Solar | 1 MW | ~21 km |
| USS Horne South Solar LLC CSG | Solar | 1 MW | ~22 km |
See all wind plants in Minnesota or browse all plants in Minnesota.