Mustang Two
A 150 MW solar power plant in Kings, California, owned by RE Mustang Two LLC, commissioned in 2020.
Facility nameplate · EIA Plant ID 62015Solar
Nameplate capacity
150 MW
Primary fuel
Solar
Commissioned
2020
Time in queue (2014→2020)
6.6 yrs
Owner
RE Mustang Two LLC
Location
Kings, California
Coordinates
Generation (2024)
384.1 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
2
This facility was matched to a CAISO interconnection request (LBNL Queued Up): queued 2014, commercial operation 2020 — 6.6 years in the queue. See the CAISO queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2020 | 42 | |
| 2021 | 394.1 | |
| 2022 | 359.1 | |
| 2023 | 381.4 | |
| 2024 | 384.1 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| RE Mustang LLC | Solar | 175 MW | ~1 km |
| Westside Solar Power PV1 | Solar | 2 MW | ~1 km |
| Slate Hybrid | Solar | 440.3 MW | ~1 km |
| RE Kent South, LLC | Solar | 20 MW | ~1 km |
| Almond | Solar | 19.9 MW | ~1 km |
| Henrietta D Energy Storage LLC | Storage | 10 MW | ~2 km |
See all solar plants in California or browse all plants in California.