Pilgrim Stage Wind Park

A 10.5 MW wind power plant in Twin Falls, Idaho, owned by Idaho Wind Partners 1 LLC, commissioned in 2011.

Facility nameplate · EIA Plant ID 56440Wind
Nameplate capacity
10.5 MW
Primary fuel
Wind
Commissioned
2011
Location
Twin Falls, Idaho
Generation (2024)
34.3 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1

Reported annual generation

YearGWh
201528
201631.1
201729.9
201833.5
201931.7
202034.4
202135.4
202231.4
202331.8
202434.3

Nearby power plants

PlantFuelCapacityDistance
Yahoo CreekWind21 MW~3 km
Payne's FerryWind21 MW~3 km
Camp ReedWind22.5 MW~4 km
Oregon Trail Wind ParkWind13.5 MW~5 km
Tuana Gulch Wind ParkWind10.5 MW~5 km
Cassia WindWind8.4 MW~6 km