Pioneer Wind Park, LLC
A 80 MW wind power plant in Converse, Wyoming, owned by AES Distributed Energy, commissioned in 2016.
Facility nameplate · EIA Plant ID 60259Wind
Nameplate capacity
80 MW
Primary fuel
Wind
Commissioned
2016
Owner
AES Distributed Energy
Location
Converse, Wyoming
Coordinates
Generation (2024)
273 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2016 | 75 | |
| 2017 | 269.2 | |
| 2018 | 252.7 | |
| 2019 | 282.1 | |
| 2020 | 292.2 | |
| 2021 | 242.7 | |
| 2022 | 218.4 | |
| 2023 | 226.3 | |
| 2024 | 273 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Dave Johnston | Coal | 816.7 MW | ~14 km |
| Top of the World Windpower Project | Wind | 200 MW | ~23 km |
| Glenrock | Wind | 165.6 MW | ~32 km |
| Campbell Hill Windpower | Wind | 99 MW | ~34 km |
| Casper Wind Farm | Wind | 17 MW | ~34 km |
| Rolling Hills | Wind | 115.8 MW | ~37 km |