Pittsfield 44 - M&W PV
A 1.2 MW solar power plant in Berkshire, Massachusetts, owned by NSTAR Electric Company, commissioned in 2018.
Facility nameplate · EIA Plant ID 62264Solar
Nameplate capacity
1.2 MW
Primary fuel
Solar
Commissioned
2018
Location
Berkshire, Massachusetts
Coordinates
Generation (2024)
1.7 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
Location
Berkshire, Massachusetts · 42.4874, -73.2158
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2018 | 0.4 | |
| 2019 | 1.6 | |
| 2020 | 1.7 | |
| 2021 | 1.5 | |
| 2022 | 1.7 | |
| 2023 | 1.5 | |
| 2024 | 1.7 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Partridge Solar | Solar | 7.5 MW | ~0 km |
| Skyline Solar | Solar | 7.5 MW | ~2 km |
| East Acres Solar NG, LLC | Solar | 5.8 MW | ~2 km |
| Pittsfield Generating LP | Natural Gas | 175.5 MW | ~3 km |
| Downing Parkway Solar | Solar | 2.3 MW | ~4 km |
| 401 South | Storage | 1.5 MW | ~4 km |