Pullman Solar, LLC
A 20 MW solar power plant in Allegan, Michigan, owned by AES Distributed Energy, commissioned in 2022.
Facility nameplate · EIA Plant ID 64581Solar
Nameplate capacity
20 MW
Primary fuel
Solar
Commissioned
2022
Location
Allegan, Michigan
Coordinates
Generation (2024)
38 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
Location
Allegan, Michigan · 42.4716, -86.0969
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2022 | 0 | |
| 2023 | 35.5 | |
| 2024 | 38 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Allegan Dam | Hydroelectric | 2.6 MW | ~16 km |
| New Covert Generating Facility | Natural Gas | 1.18 GW | ~23 km |
| Palisades | Nuclear | 811.8 MW | ~24 km |
| 491 E 48th Street | Natural Gas | 161.7 MW | ~32 km |
| Otsego Mill Power Plant | Natural Gas | 21.2 MW | ~33 km |
| Watervliet PV | Solar | 4.6 MW | ~33 km |