Red Mesa Solar Project

A 72 MW solar power plant in San Juan, Utah, owned by NTUA Generation - Utah, LLC, commissioned in 2023.

Facility nameplate · EIA Plant ID 66404Solar
Nameplate capacity
72 MW
Primary fuel
Solar
Commissioned
2023
Owner
NTUA Generation - Utah, LLC
Location
San Juan, Utah
Generation (2024)
191.7 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

Reported annual generation

YearGWh
2023152.8
2024191.7

Nearby power plants

PlantFuelCapacityDistance
Cortez Solar 2, LLCSolar5 MW~76 km
Cortez Solar 3, LLCSolar2 MW~76 km
TowaocHydroelectric11.4 MW~82 km
Cortez Solar 1, LLCSolar2.2 MW~83 km
Kayenta Solar ProjectSolar55.3 MW~85 km
Latigo Wind ParkWind62.1 MW~85 km

See all solar plants in Utah or browse all plants in Utah.