Sandrini Solar 200

A 200 MW solar power plant in Kern, California, owned by EDPR CA Solar Park LLC, commissioned in 2024.

Facility nameplate · EIA Plant ID 65663Solar
Nameplate capacity
200 MW
Primary fuel
Solar
Commissioned
2024
Time in queue (20152024)
9.3 yrs
Owner
EDPR CA Solar Park LLC
Location
Generation (2024)
42.9 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a Non-ISO West interconnection request (LBNL Queued Up): queued 2015, commercial operation 2024 9.3 years in the queue. See the West queue or typical durations.

Nearby power plants

PlantFuelCapacityDistance
Lakeview Battery Storage FacilityStorage1.2 MW~1 km
Sandrini Solar 100Solar100 MW~5 km
ABEC Bidart-Old River LLCBiomass2 MW~9 km
Adobe SolarSolar20 MW~9 km
ABEC #4 dba CE&S DairyBiomass1 MW~10 km
AVI BakersfieldSolar2.2 MW~12 km