Seven Cowboy Wind Project, LLC
A 301.7 MW wind power plant in Washita, Oklahoma, owned by Seven Cowboy Wind Project, LLC, commissioned in 2023.
Facility nameplate · EIA Plant ID 65971Wind
Nameplate capacity
301.7 MW
Primary fuel
Wind
Commissioned
2023
Time in queue (2016→2023)
7 yrs
Owner
Seven Cowboy Wind Project, LLC
Location
Washita, Oklahoma
Coordinates
Generation (2024)
989.9 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
This facility was matched to a SPP interconnection request (LBNL Queued Up): queued 2016, commercial operation 2023 — 7 years in the queue. See the SPP queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2023 | 751.4 | |
| 2024 | 989.9 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Rocky Ridge Wind Project | Wind | 148.8 MW | ~13 km |
| Little Elk Wind Project LLC | Wind | 74 MW | ~18 km |
| Red Hills Wind Project LLC | Wind | 123 MW | ~43 km |
| Weatherford Wind Energy Center | Wind | 147 MW | ~47 km |
| Mangum | Natural Gas | 6.7 MW | ~52 km |
| Blue Canyon Windpower II | Wind | 151.4 MW | ~60 km |
See all wind plants in Oklahoma or browse all plants in Oklahoma.