A 2.5 MW solar power plant in San Bernardino, California, owned by Southern California Edison Co, commissioned in 2012, retired in 2023.
Facility nameplate · EIA Plant ID 57221Retired 2023Solar
Nameplate capacity
2.5 MW
Primary fuel
Solar
Commissioned
2012
Owner
Southern California Edison Co
Location
San Bernardino, California
Coordinates
Generation (2023)
0.1 GWh
Status
Retired
Retired
2023
Technology
Solar Photovoltaic
Units
5
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2015 | 4.5 | |
| 2016 | 4 | |
| 2017 | 4.1 | |
| 2018 | 3.9 | |
| 2019 | 3.2 | |
| 2020 | 2.3 | |
| 2021 | 3.4 | |
| 2022 | 3.2 | |
| 2023 | 0.1 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Mountainview Generating Station | Natural Gas | 1.04 GW | ~1 km |
| IGS KSBD | Solar | 4.3 MW | ~2 km |
| Chambers 4 - Redland LGB4 | Solar | 1.9 MW | ~2 km |
| Kohls San Bernardino Solar Facility | Solar | 1 MW | ~4 km |
| Chambers 4 - San Bernardino SNA7 | Solar | 2 MW | ~4 km |