Thunderhead Wind Energy LLC
A 300 MW wind power plant in Antelope, Nebraska, owned by Invenergy Services LLC, commissioned in 2022.
Facility nameplate · EIA Plant ID 62956Wind
Nameplate capacity
300 MW
Primary fuel
Wind
Commissioned
2022
Time in queue (2015→2022)
7.6 yrs
Owner
Invenergy Services LLC
Location
Antelope, Nebraska
Coordinates
Generation (2024)
1,178.9 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
This facility was matched to a SPP interconnection request (LBNL Queued Up): queued 2015, commercial operation 2022 — 7.6 years in the queue. See the SPP queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2022 | 200.4 | |
| 2023 | 1,138.2 | |
| 2024 | 1,178.9 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Prairie Breeze II | Wind | 73.4 MW | ~9 km |
| Prairie Breeze III | Wind | 35.8 MW | ~9 km |
| Prairie Breeze | Wind | 206.5 MW | ~18 km |
| Upstream Wind Energy LLC | Wind | 202.5 MW | ~26 km |
| Laredo Ridge Wind LLC | Wind | 79.9 MW | ~27 km |
| TPW Petersburg | Wind | 40.5 MW | ~32 km |
See all wind plants in Nebraska or browse all plants in Nebraska.