Upland

A 7.3 MW solar power plant under construction in Plymouth, Massachusetts, owned by Greenbacker Renewable Energy Corporation, expected online 2024.

Facility nameplate · EIA Plant ID 67276Under constructionSolar
Nameplate capacity
7.3 MW
Primary fuel
Solar
Commissioned
Owner
Greenbacker Renewable Energy Corporation
Location
Plymouth, Massachusetts
Other fuels
Storage
Status
Under construction
Expected online
2024
Technology
Solar Photovoltaic
Units
2

Nearby power plants

PlantFuelCapacityDistance
Brook Street Solar 1 CSGSolar5 MW~1 km
Plymouth Site 1Solar4 MW~1 km
Plympton Main Street Solar, LLCSolar5 MW~2 km
Spring Street Solar 1 CSGSolar2 MW~3 km
Carver MA 1 Community SolarSolar2 MW~3 km
Plympton Lake Street SolarSolar2.4 MW~4 km