Wanship
A 1.9 MW hydroelectric power plant in Summit, Utah, owned by Weber Basin Water Conserv Dist, commissioned in 1958.
Facility nameplate · EIA Plant ID 3698Hydroelectric
Nameplate capacity
1.9 MW
Primary fuel
Hydroelectric
Commissioned
1958
Owner
Weber Basin Water Conserv Dist
Location
Summit, Utah
Coordinates
Generation (2024)
9 GWh
Status
Operating
Technology
Conventional Hydroelectric
Units
1
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2015 | 6 | |
| 2016 | 5.6 | |
| 2017 | 7 | |
| 2018 | 5.9 | |
| 2019 | 6.2 | |
| 2020 | 6.6 | |
| 2021 | 2.7 | |
| 2022 | 6.4 | |
| 2023 | 12.3 | |
| 2024 | 9 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Echo Dam | Hydroelectric | 4.4 MW | ~20 km |
| Jordanelle Dam Hydroelectric Project | Hydroelectric | 13 MW | ~22 km |
| Snake Creek | Hydroelectric | 1.2 MW | ~28 km |
| Snowbird Power Plant | Natural Gas | 6.5 MW | ~31 km |
| Heber City | Natural Gas | 17.5 MW | ~32 km |
| Lake Creek Dam | Hydroelectric | 1.5 MW | ~34 km |
See all hydroelectric plants in Utah or browse all plants in Utah.