Weber State University - Davis Campus PV

A 1.3 MW solar power plant in Davis, Utah, owned by Tesla Inc., commissioned in 2017.

Facility nameplate · EIA Plant ID 60821Solar
Nameplate capacity
1.3 MW
Primary fuel
Solar
Commissioned
2017
Owner
Tesla Inc.
Location
Davis, Utah
Generation (2024)
2.7 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

Reported annual generation

YearGWh
20170
20182.4
20192.2
20202.1
20212.6
20222.8
20232.5
20242.7

Nearby power plants

PlantFuelCapacityDistance
Hill AFB LFG Facility, Bldg #737Waste2.3 MW~4 km
WeberHydroelectric3.8 MW~9 km
SF Auto O1Solar3.4 MW~12 km
GatewayHydroelectric4 MW~13 km
PioneerHydroelectric5 MW~16 km
Pine View DamHydroelectric1.8 MW~21 km

See all solar plants in Utah or browse all plants in Utah.