WED Coventry 4

A 1.5 MW wind power plant in Kent, Rhode Island, owned by WED Coventry Four, LLC, commissioned in 2016.

Facility nameplate · EIA Plant ID 59306Wind
Nameplate capacity
1.5 MW
Primary fuel
Wind
Commissioned
2016
Owner
WED Coventry Four, LLC
Location
Generation (2024)
2.3 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1

Reported annual generation

YearGWh
20160.9
20172.7
20182.6
20192.6
20202.5
20212.5
20222.5
20232.2
20242.3

Nearby power plants

PlantFuelCapacityDistance
WED Coventry 3Wind1.5 MW~1 km
WED Coventry Seven, LLCSolar3 MW~1 km
WED Coventry 1Wind1.5 MW~2 km
WED Coventry 2Wind4.5 MW~2 km
WED Coventry 6Wind4.5 MW~2 km
WED Coventry 5Wind1.5 MW~4 km