Alabama · Gas

Proposed gas projects in Alabama

There are 13 proposed gas projects in Alabama's interconnection queue, totaling 4.35 GW of requested capacity. The largest is Queue 416 at 780 MW, and the median planned online year is 2030.

13
Proposed projects
4.35 GW
Requested capacity
334.6 MW
Average project size
2030
Median planned online year

All proposed gas projects in Alabama

TypeRegionIA Status
Queue 416
416
GasSoutheastColbertIA Executed780 MW20202022
Queue 25-IC-1382
25-IC-1382
GasSoutheastMobileCluster Study707 MW20252031
Queue IC-1158susp.
IC-1158
GasSoutheastMobile685 MW20232028
Queue 25RSC-011
25RSC-011
GasSoutheastMorganIn Progress (unknown study)528 MW20252031
Queue IC-1159susp.
IC-1159
GasSoutheastShelby403.1 MW20232030
Queue IC-1160susp.
IC-1160
GasSoutheastShelby403.1 MW20232030
Queue 25-IC-1320A
25-IC-1320A
GasSoutheastLeeFacility Study240 MW20252029
Queue 25-IC-1317
25-IC-1317
GasSoutheastAutaugaCluster Study229 MW20252029
Queue 25-IC-1318
25-IC-1318
GasSoutheastAutaugaCluster Study111 MW20252031
Queue 25-IC-1319
25-IC-1319
GasSoutheastAutaugaCluster Study111 MW20252032
Queue 25-IC-1321
25-IC-1321
GasSoutheastLeeCluster Study111 MW20252029
Queue IC-1012
IC-1012
GasSoutheastAutaugaSystem Impact Study27 MW2020
Queue 25-IC-1344
25-IC-1344
GasSoutheastMobileCluster Study14 MW20252028

Browse Alabama's full interconnection queue. Compare with operating capacity: 26 operating natural gas plants in Alabama. Nationwide: Natural Gas plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).