Proposed battery projects in Florida

There are 10 proposed battery projects in Florida's interconnection queue, totaling 1.77 GW of requested capacity. The largest is FPL project at 400 MW, and the median planned online year is 2027.

10
Proposed projects
1.77 GW
Requested capacity
176.8 MW
Average project size
2027
Median planned online year

All proposed battery projects in Florida

TypeRegionIA Status
FPL project
620
BatterySoutheastBaySystem Impact Study400 MW20242026
Duke Energy Florida, LLC project
292
BatterySoutheastPinellasConstruction225 MW20212025
Malta Project
202311
BatterySoutheastBrevardFacility Study225 MW20232026
FPL project
615
BatterySoutheastPutnamSystem Impact Study200 MW20242027
Duke Energy Florida, LLC project
FC100009
BatterySoutheastPascoIA Pending199 MW20242029
Duke Energy Florida, LLC project
FC100380
BatterySoutheastCitrusIn Progress (unknown study)199 MW20252030
Duke Energy Florida, LLC project
327
BatterySoutheastCitrusConstruction100 MW20232027
Duke Energy Florida, LLC project
FC100008
BatterySoutheastHighlandsIA Pending100 MW20242029
Duke Energy Florida, LLC project
FC100381
BatterySoutheastLeonIn Progress (unknown study)100 MW20252031
Queue 120
120
BatterySoutheastPolkCluster Study20 MW20252027

Browse Florida's full interconnection queue. Compare with operating capacity: 7 operating storage plants in Florida. Nationwide: Storage plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).