Georgia · Battery
Proposed battery projects in Georgia
There are 27 proposed battery projects in Georgia's interconnection queue, totaling 7.29 GW of requested capacity. The largest is Queue 25-IC-1374 at 600 MW, and the median planned online year is 2028.
27
Proposed projects
7.29 GW
Requested capacity
270 MW
Average project size
2028
Median planned online year
All proposed battery projects in Georgia
| Type | ||||
|---|---|---|---|---|
| Queue 25-IC-1374 25-IC-1374 | Battery | 600 MW | 2025 | 2029 |
| Queue IC-974susp. IC-974 | Battery | 600 MW | 2021 | 2025 |
| Queue 25-IC-1311 25-IC-1311 | Battery | 500 MW | 2025 | 2028 |
| Queue IC-1170susp. IC-1170 | Battery | 500 MW | 2023 | 2030 |
| Queue IC-1247 IC-1247 | Battery | 500 MW | 2024 | 2028 |
| Queue 25-IC-1385 25-IC-1385 | Battery | 450 MW | 2025 | 2030 |
| Queue 25-IC-1375 25-IC-1375 | Battery | 325 MW | 2025 | 2031 |
| Queue IC-1279 IC-1279 | Battery | 320 MW | 2024 | 2028 |
| Queue IC-1271 IC-1271 | Battery | 265 MW | 2024 | 2026 |
| Queue IC-906 IC-906 | Battery | 265 MW | 2020 | 2026 |
| Queue IC-1144susp. IC-1144 | Battery | 260 MW | 2023 | 2028 |
| Queue 25-IC-1312 25-IC-1312 | Battery | 250 MW | 2025 | 2028 |
| Queue 25-IC-1313 25-IC-1313 | Battery | 250 MW | 2025 | 2028 |
| Queue 25-IC-1334 25-IC-1334 | Battery | 250 MW | 2025 | 2029 |
| Queue IC-1222 IC-1222 | Battery | 250 MW | 2023 | 2027 |
| Queue IC-1223 IC-1223 | Battery | 250 MW | 2023 | 2028 |
| Queue IC-1187 IC-1187 | Battery | 220 MW | 2023 | 2027 |
| Queue IC-1272 IC-1272 | Battery | 200 MW | 2024 | 2030 |
| Union City Storage I GI-132 | Battery | 200 MW | 2019 | 2022 |
| Queue 25-IC-1314 25-IC-1314 | Battery | 192.5 MW | 2025 | 2028 |
| Queue IC-905 IC-905 | Battery | 150 MW | 2020 | 2027 |
| Dougherty County BESS GI-211 | Battery | 120 MW | 2025 | — |
| Queue 25-IC-1343 25-IC-1343 | Battery | 100 MW | 2025 | 2028 |
| Queue IC-1116 IC-1116 | Battery | 100 MW | 2023 | 2027 |
| Union City Storage II GI-133 | Battery | 100 MW | 2019 | 2022 |
| Queue IC-1267 IC-1267 | Battery | 57.5 MW | 2024 | 2026 |
| Queue IC-1280 IC-1280 | Battery | 15 MW | 2024 | 2027 |
Browse Georgia's full interconnection queue. Compare with operating capacity: 1 operating storage plants in Georgia. Nationwide: Storage plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).