Georgia · Solar + Battery

Proposed solar + battery projects in Georgia

There are 42 proposed solar + battery projects in Georgia's interconnection queue, totaling 7.62 GW of requested capacity. The largest is Queue IC-942 at 1.20 GW, and the median planned online year is 2026.

42
Proposed projects
7.62 GW
Requested capacity
181.5 MW
Average project size
2026
Median planned online year

All proposed solar + battery projects in Georgia

TypeRegionIA Status
Queue IC-942susp.
IC-942
Solar + BatterySoutheastGlynn1.20 GW20212025
TOCE GA Solar 4
GI-189
Solar + BatterySoutheastJeffersonFacility Study325 MW20242027
Queue IC-932susp.
IC-932
Solar + BatterySoutheastGlynn250 MW20202024
Queue IC-933susp.
IC-933
Solar + BatterySoutheastGlynn250 MW20202024
Rock House Solar
GI-160
Solar + BatterySoutheastMcduffieFacility Study250 MW20222025
Thundering Springs
GI-130
Solar + BatterySoutheastLaurensFacility Study240 MW20192023
Pecan Energy Storage
GI-187
Solar + BatterySoutheastMitchellFacility Study207.6 MW20232029
Washington County Solar
GI-197
Solar + BatterySoutheastWashingtonSystem Impact Study203 MW20242027
Queue IC-1013susp.
IC-1013
Solar + BatterySoutheastOglethorpe200 MW20222025
Queue IC-1042susp.
IC-1042
Solar + BatterySoutheastRockdale200 MW20222026
Queue IC-1265
IC-1265
Solar + BatterySoutheastLaurensIA Executed200 MW20242028
Queue IC-839
IC-839
Solar + BatterySoutheastSumterIA Executed200 MW20192027
Live Oak Solar
GI-175
Solar + BatterySoutheastLaurensFacility Study200 MW20232026
Oakhurst Solar Farm
GI-100
Solar + BatterySoutheastMitchellFacility Study200 MW20172021
Queue 25-IC-1383
25-IC-1383
Solar + BatterySoutheastDoughertyFacility Study199 MW20252030
Beaver Creek Solar
GI-184
Solar + BatterySoutheastBaldwinFacility Study183 MW20232027
Queue 25-IC-1339
25-IC-1339
Solar + BatterySoutheastHancockCluster Study165 MW20252029
Crawford Solar
GI-164
Solar + BatterySoutheastCrawfordSystem Impact Study160 MW20222025
Red Dirt Solar
GI-172
Solar + BatterySoutheastTalbotFacility Study153 MW20232026
Queue IC-1006susp.
IC-1006
Solar + BatterySoutheastLiberty150 MW20212026
Queue IC-1099susp.
IC-1099
Solar + BatterySoutheastPulaski150 MW20222026
Queue IC-1100susp.
IC-1100
Solar + BatterySoutheastPulaski150 MW20222026
Queue IC-1276
IC-1276
Solar + BatterySoutheastMitchellIA Executed150 MW20242028
Queue IC-964susp.
IC-964
Solar + BatterySoutheastEmanuel150 MW20212025
Cherry Blossom Solar
GI-142
Solar + BatterySoutheastTwiggsFacility Study150 MW20202023
Cherry Tree Solar
GI-159
Solar + BatterySoutheastWashingtonFacility Study150 MW20212025
Crossroads Solar
GI-152
Solar + BatterySoutheastLibertyFacility Study150 MW20212024
Dellwood Solar
GI-149
Solar + BatterySoutheastEmanuelFacility Study150 MW20212024
Limestone Solar
GI-118
Solar + BatterySoutheastMaconFacility Study150 MW20192021
Spain Energy Center
GI-190
Solar + BatterySoutheastBrooksFacility Study141 MW20242028
Queue IC-966
IC-966
Solar + BatterySoutheastDecaturIA Executed130 MW20212024
Meriwether Panther Solar
GI-161
Solar + BatterySoutheastMeriwetherFacility Study125 MW20222026
Queue IC-1068
IC-1068
Solar + BatterySoutheastEmanuelIA Executed124 MW20222027
Two Rivers Solar
GI-162
Solar + BatterySoutheastCamdenFacility Study102 MW20222027
Queue IC-980susp.
IC-980
Solar + BatterySoutheastOglethorpe100 MW20212024
Queue 25-IC-1387
25-IC-1387
Solar + BatterySoutheastSumterFacility Study92 MW20252028
Queue 25-IC-1384
25-IC-1384
Solar + BatterySoutheastTiftFacility Study88 MW20252029
Long Cane Solar
GI-153
Solar + BatterySoutheastTroupSystem Impact Study80 MW20212024
Scarboro Solar
GI-200
Solar + BatterySoutheastMillerSystem Impact Study75 MW20242031
Queue IC-1103
IC-1103
Solar + BatterySoutheastEmanuelIA Executed64 MW20222027
Queue IC-903
IC-903
Solar + BatterySoutheastLibertyIA Executed13 MW20202023
Queue IC-1199
IC-1199
Solar + BatterySoutheastLowndesIA Executed3.5 MW20232025

Browse Georgia's full interconnection queue. Compare with operating capacity: 150 operating solar plants in Georgia, 1 operating storage plants in Georgia. Nationwide: Solar plants nationwide, Storage plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).