Minnesota · Solar + Battery
Proposed solar + battery projects in Minnesota
There are 5 proposed solar + battery projects in Minnesota's interconnection queue, totaling 978 MW of requested capacity. The largest is Queue J3002 at 288 MW, and the median planned online year is 2025.
5
Proposed projects
978 MW
Requested capacity
195.6 MW
Average project size
2025
Median planned online year
All proposed solar + battery projects in Minnesota
| Type | ||||
|---|---|---|---|---|
| Queue J3002 J3002 | Solar + Battery | 288 MW | 2022 | 2025 |
| Queue J1846 J1846 | Solar + Battery | 200 MW | 2021 | 2024 |
| Queue J2219 J2219 | Solar + Battery | 180 MW | 2021 | 2028 |
| Queue J3742 J3742 | Solar + Battery | 160 MW | 2024 | 2028 |
| Queue J1572 J1572 | Solar + Battery | 150 MW | 2020 | 2023 |
Browse Minnesota's full interconnection queue. Compare with operating capacity: 516 operating solar plants in Minnesota, 3 operating storage plants in Minnesota. Nationwide: Solar plants nationwide, Storage plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).