Nebraska · Battery
Proposed battery projects in Nebraska
There are 19 proposed battery projects in Nebraska's interconnection queue, totaling 2.68 GW of requested capacity. The largest is Queue GEN-2021-043 at 250 MW, and the median planned online year is 2028.
19
Proposed projects
2.68 GW
Requested capacity
140.9 MW
Average project size
2028
Median planned online year
All proposed battery projects in Nebraska
| Type | ||||
|---|---|---|---|---|
| Queue GEN-2021-043 GEN-2021-043 | Battery | 250 MW | 2021 | 2030 |
| Queue GEN-2024-372 GEN-2024-372 | Battery | 250 MW | 2025 | 2028 |
| Queue GEN-2026-SR20 GEN-2026-SR20 | Battery | 225 MW | 2026 | 2028 |
| Queue GEN-2018-025 GEN-2018-025 | Battery | 200 MW | 2018 | 2028 |
| Queue GEN-2018-033 GEN-2018-033 | Battery | 200 MW | 2018 | 2029 |
| Queue GEN-2021-040 GEN-2021-040 | Battery | 200 MW | 2021 | 2029 |
| Queue GEN-2024-173 GEN-2024-173 | Battery | 200 MW | 2025 | 2028 |
| Queue GEN-2024-051 GEN-2024-051 | Battery | 170 MW | 2024 | 2028 |
| Queue GEN-2025-SR31 GEN-2025-SR31 | Battery | 170 MW | 2025 | 2026 |
| Queue GEN-2024-065 GEN-2024-065 | Battery | 150 MW | 2024 | 2029 |
| Queue GEN-2023-SR7 GEN-2023-SR7 | Battery | 135 MW | 2022 | 2024 |
| Queue GEN-2018-037 GEN-2018-037 | Battery | 100 MW | 2018 | 2030 |
| Queue GEN-2021-039 GEN-2021-039 | Battery | 100 MW | 2021 | 2030 |
| Queue GEN-2024-SR10 GEN-2024-SR10 | Battery | 80 MW | 2024 | 2026 |
| Queue GEN-2021-048 GEN-2021-048 | Battery | 75 MW | 2021 | 2029 |
| Queue GEN-2024-SR8 GEN-2024-SR8 | Battery | 70 MW | 2024 | 2026 |
| Queue GEN-2023-SR19 GEN-2023-SR19 | Battery | 50 MW | 2023 | 2027 |
| Queue GEN-2025-SR5 GEN-2025-SR5 | Battery | 40 MW | 2025 | 2026 |
| Queue GEN-2017-198 GEN-2017-198 | Battery | 11.6 MW | 2017 | 2027 |
Browse Nebraska's full interconnection queue. Compare with operating capacity: 2 operating storage plants in Nebraska. Nationwide: Storage plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition). Data: LBNL backbone through December 31, 2025; ISO-region statuses refreshed monthly (last: July 2026); non-ISO West and Southeast as of the LBNL edition.