New Mexico · Battery
Proposed battery projects in New Mexico
There are 32 proposed battery projects in New Mexico's interconnection queue, totaling 4.74 GW of requested capacity. The largest is Queue IA-PNM-2023-11 at 500 MW, and the median planned online year is 2026.
32
Proposed projects
4.74 GW
Requested capacity
148.1 MW
Average project size
2026
Median planned online year
All proposed battery projects in New Mexico
| Type | ||||
|---|---|---|---|---|
| Queue IA-PNM-2023-11 IA-PNM-2023-11 | Battery | 500 MW | 2023 | 2026 |
| Queue IA-PNM-2025-09 IA-PNM-2025-09 | Battery | 400 MW | 2025 | 2029 |
| Va400B Q25-LG-6-13-6 | Battery | 400 MW | 2025 | 2028 |
| Es300B Q25-LG-6-13-5 | Battery | 300 MW | 2025 | 2028 |
| Queue IA-PNM-2023-02 IA-PNM-2023-02 | Battery | 200 MW | 2023 | 2027 |
| Queue IA-PNM-2023-03 IA-PNM-2023-03 | Battery | 200 MW | 2023 | 2027 |
| Queue GI-SISS-2025-03 GI-SISS-2025-03 | Battery | 200 MW | 2025 | 2027 |
| Juan Tabo Grid IA-PNM-2021-02 | Battery | 200 MW | 2021 | 2021 |
| Sun Lasso Energy Center IA-PNM-2021-04 | Battery | 152.5 MW | 2021 | 2024 |
| PNM – Generation project IA-PNM-2019-19 | Battery | 150 MW | 2019 | 2021 |
| AES Renewable Holdings project IA-PNM-2020-17 | Battery | 150 MW | 2020 | 2023 |
| EsVolta Development project IA-PNM-2021-16 | Battery | 150 MW | 2021 | 2024 |
| Queue IA-PNM-2023-18 IA-PNM-2023-18 | Battery | 150 MW | 2023 | 2026 |
| Queue IA-PNM-2025-13 IA-PNM-2025-13 | Battery | 150 MW | 2025 | 2027 |
| Corazon Energy Storage IA-PNM-2021-13 | Battery | 150 MW | 2021 | 2024 |
| Queue IA-PNM-2025-12 IA-PNM-2025-12 | Battery | 115 MW | 2025 | 2027 |
| Queue GEN-2024-295 GEN-2024-295 | Battery | 115 MW | 2025 | 2030 |
| Queue IA-PNM-2019-18susp. IA-PNM-2019-18 | Battery | 100 MW | 2019 | 2022 |
| Queue IA-PNM-2022-11 IA-PNM-2022-11 | Battery | 100 MW | 2022 | 2024 |
| Queue IA-PNM-2024-01 IA-PNM-2024-01 | Battery | 100 MW | 2024 | 2029 |
| Queue IA-PNM-2025-11 IA-PNM-2025-11 | Battery | 100 MW | 2025 | 2028 |
| Zinnia Storage IA-PNM-2020-13 | Battery | 100 MW | 2020 | 2023 |
| Queue GEN-2024-310 GEN-2024-310 | Battery | 75 MW | 2025 | 2030 |
| Queue GEN-2025-SR29 GEN-2025-SR29 | Battery | 75 MW | 2025 | 2027 |
| Queue GEN-2018-052 GEN-2018-052 | Battery | 70 MW | 2018 | 2027 |
| Queue IA-PNM 2022-10 IA-PNM 2022-10 | Battery | 50 MW | 2022 | 2024 |
| Queue GEN-2025-SR27 GEN-2025-SR27 | Battery | 50 MW | 2025 | 2026 |
| Queue GEN-2025-SR32 GEN-2025-SR32 | Battery | 50 MW | 2025 | 2026 |
| AN50B LG-24-3-9 | Battery | 50 MW | 2024 | 2027 |
| Zinnia Storage IA-PNM-2021-01 | Battery | 50 MW | 2021 | 2024 |
| Belen Energy IA-PNM-2021-17 | Battery | 49.5 MW | 2021 | 2025 |
| Queue GEN-2024-SR14 GEN-2024-SR14 | Battery | 36 MW | 2024 | 2026 |
Browse New Mexico's full interconnection queue. Compare with operating capacity: 2 operating storage plants in New Mexico. Nationwide: Storage plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition). Data: LBNL backbone through December 31, 2025; ISO-region statuses refreshed monthly (last: July 2026); non-ISO West and Southeast as of the LBNL edition.