New Mexico · Solar

Proposed solar projects in New Mexico

There are 29 proposed solar projects in New Mexico's interconnection queue, totaling 3.85 GW of requested capacity. The largest is Queue IA-PNM-2023-07 at 300 MW, and the median planned online year is 2026.

29
Proposed projects
3.85 GW
Requested capacity
132.7 MW
Average project size
2026
Median planned online year

All proposed solar projects in New Mexico

TypeRegionIA Status
Queue IA-PNM-2023-07
IA-PNM-2023-07
SolarWestSanta FeCluster Study300 MW20232025
Queue GEN-2024-159
GEN-2024-159
SolarSPPRooseveltSystem Impact Study300 MW20252029
AW300S
LG-23-3-2
SolarWestSierraIA Executed300 MW20232029
Queue GEN-2024-079
GEN-2024-079
SolarSPPCurrySystem Impact Study250 MW20242029
Queue GEN-2024-080
GEN-2024-080
SolarSPPCurrySystem Impact Study250 MW20242029
Queue IA-PNM-2024-04
IA-PNM-2024-04
SolarWestSanta FeCluster Study230 MW20242028
Queue GEN-2024-311
GEN-2024-311
SolarSPPChavesSystem Impact Study225 MW20252030
Old Route 66 Power
IA-PNM-2021-08
SolarWestGuadalupeIA Executed200 MW20212024
Queue IA-PNM-2023-16
IA-PNM-2023-16
SolarWestRooseveltCluster Study199 MW20232028
Queue GEN-2024-GR3
GEN-2024-GR3
SolarSPPLeaIA Pending196 MW20242027
Queue GEN-2019-003
GEN-2019-003
SolarSPPRooseveltIA Executed150 MW20192027
Huning Energy
IA-PNM-2021-19
SolarWestValencia150 MW20212025
NMRD Data Center IV
IA-PNM-2017-10
SolarWestSandovalIA Executed140 MW20172022
Queue GI-DISIS-2021-01susp.
GI-DISIS-2021-01
SolarWestHardingSuspended120 MW20212028
Queue GEN-2016-121
GEN-2016-121
SolarSPPLeaIA Executed110 MW20162026
DESRI Rockmont Development projectsusp.
IA-PNM-2018-03
SolarWestSan JuanSuspended100 MW20182021
AN100S
LG-24-3-10
SolarWestLunaIA Executed100 MW20242027
Queue IA-PNM-2017-15
IA-PNM-2017-15
SolarWestSan JuanIA Executed95.6 MW20172022
Queue GEN-2018-004
GEN-2018-004
SolarSPPLeaIA Executed75 MW20182027
Queue GEN-2023-GR4
GEN-2023-GR4
SolarSPPLeaIA Executed72 MW20232026
NM Renewable Development project
IA-PNM-2017-06
SolarWestSandovalIA Executed50 MW20172022
NM Renewable Development project
IA-PNM-2017-07
SolarWestSandovalIA Executed50 MW20172022
Queue GEN-2019-021
GEN-2019-021
SolarSPPRooseveltIA Executed50 MW20192027
NMRD Data Center IV
IA-PNM-2017-09
SolarWestSanta FeIA Executed50 MW20172022
Queue IA-PNM-2012-04
IA-PNM-2012-04
SolarWestGuadalupe CtyIA Executed40 MW20122016
Queue GEN-2024-273
GEN-2024-273
SolarSPPLeaSystem Impact Study16.2 MW20252026
Queue SGI-PNM-2017-08
SGI-PNM-2017-08
SolarWestLunaIA Executed11 MW20172019
NextEra Energy project
IA-PNM-2017-01
SolarWestCibolaIA Executed10 MW20172021
Queue SGI-PNM-2017-09
SGI-PNM-2017-09
SolarWestLunaIA Executed8.2 MW20172019

Browse New Mexico's full interconnection queue. Compare with operating capacity: 86 operating solar plants in New Mexico. Nationwide: Solar plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).