Oklahoma · Gas

Proposed gas projects in Oklahoma

There are 31 proposed gas projects in Oklahoma's interconnection queue, totaling 15.05 GW of requested capacity. The largest is Queue GEN-2024-340 at 1.40 GW, and the median planned online year is 2029.

31
Proposed projects
15.05 GW
Requested capacity
485.6 MW
Average project size
2029
Median planned online year

All proposed gas projects in Oklahoma

TypeRegionIA Status
Queue GEN-2024-340
GEN-2024-340
GasSPPCreekSystem Impact Study1.40 GW20252032
Queue GEN-2024-132
GEN-2024-132
GasSPPJohnstonSystem Impact Study1.30 GW20252031
Queue GEN-2024-341
GEN-2024-341
GasSPPPittsburgSystem Impact Study1.04 GW20252031
Queue ERAS-2025-004
ERAS-2025-004
GasSPPOklahomaIn Progress (unknown study)763 MW20252030
Queue ERAS-2025-024
ERAS-2025-024
GasSPPComancheIn Progress (unknown study)744 MW20252029
Queue ERAS-2025-026
ERAS-2025-026
GasSPPComancheIn Progress (unknown study)744 MW20252029
Queue GEN-2024-299
GEN-2024-299
GasSPPOklahomaSystem Impact Study744 MW20252032
Queue GEN-2024-128
GEN-2024-128
GasSPPCaddoSystem Impact Study690 MW20252030
Queue GEN-2024-GR5
GEN-2024-GR5
GasSPPChouteauIA Executed594 MW20242026
Queue ERAS-2025-023
ERAS-2025-023
GasSPPRogersIn Progress (unknown study)510 MW20252029
Queue ERAS-2025-010
ERAS-2025-010
GasSPPOklahomaIn Progress (unknown study)496 MW20252029
Queue GEN-2024-013
GEN-2024-013
GasSPPMcclainSystem Impact Study496 MW20242030
Queue GEN-2024-321
GEN-2024-321
GasSPPSeminoleSystem Impact Study493 MW20252030
Queue GEN-2024-GR1
GEN-2024-GR1
GasSPPOklahomaIA Executed492 MW20242026
Queue GI-103
GI-103
GasSoutheastCreekIA Executed460 MW20222027
Queue GI-104
GI-104
GasSoutheastPayneIA Executed460 MW20222026
Queue GI-129
GI-129
GasSoutheastPayneSystem Impact Study460 MW20252030
Queue GI-130
GI-130
GasSoutheastPayneSystem Impact Study460 MW20252030
Queue GEN-2024-247
GEN-2024-247
GasSPPPayneSystem Impact Study456.6 MW20252030
Queue GEN-2024-323
GEN-2024-323
GasSPPChoctawSystem Impact Study356.8 MW20252029
Queue GEN-2024-252
GEN-2024-252
GasSPPCanadianSystem Impact Study300 MW20252027
Queue GEN-2024-254
GEN-2024-254
GasSPPCanadianSystem Impact Study300 MW20252027
Queue GEN-2024-255
GEN-2024-255
GasSPPOklahomaSystem Impact Study300 MW20252027
Queue GEN-2024-293
GEN-2024-293
GasSPPOklahomaSystem Impact Study248 MW20252033
Queue ERAS-2025-003
ERAS-2025-003
GasSPPOklahomaIn Progress (unknown study)186 MW20252025
Queue GEN-2024-286
GEN-2024-286
GasSPPLe FloreSystem Impact Study136 MW20252031
Queue GEN-2024-334
GEN-2024-334
GasSPPKaySystem Impact Study124 MW20252029
Queue GEN-2023-GR1
GEN-2023-GR1
GasSPPCaddoIA Executed97.5 MW20232025
Queue GEN-2023-GR2
GEN-2023-GR2
GasSPPOklahomaIA Executed94.2 MW20232026
Queue GI-78
GI-78
GasSoutheastMayesIA Executed52 MW20192020
Queue GI-77
GI-77
GasSoutheastMayesIA Executed50 MW20192019

Browse Oklahoma's full interconnection queue. Compare with operating capacity: 37 operating natural gas plants in Oklahoma. Nationwide: Natural Gas plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).