Pennsylvania · Solar

Proposed solar projects in Pennsylvania

There are 164 proposed solar projects in Pennsylvania's interconnection queue, totaling 6.17 GW of requested capacity. The largest is Mineral Basin Solar Power at 401.6 MW, and the median planned online year is 2026.

164
Proposed projects
6.17 GW
Requested capacity
37.6 MW
Average project size
2026
Median planned online year

All proposed solar projects in Pennsylvania

TypeRegionIA Status
Mineral Basin Solar Power
1080
SolarNYISOClearfieldSystem Impact Study401.6 MW20202028
Queue AI1-040
AI1-040
SolarPJMElkFeasibility Study250 MW20222025
Moonlight Flats Solar
C24-301
SolarNYISOClearfield250 MW20242029
Queue AH2-397
AH2-397
SolarPJMSomersetFeasibility Study200 MW20222026
Cornerstone Solar
AH1-545
SolarPJMWashingtonSystem Impact Study200 MW20252025
Kimberlite Solar
C24-300
SolarNYISOClearfield175 MW20242029
Trestle Solar Farm, LLC project
AG2-176
SolarPJMCrawfordSystem Impact Study150 MW20252024
Ridgeway Solar
AE2-113
SolarPJMMckeanIA Executed120 MW20192026
Shorebird Solarsusp.
AE2-344
SolarPJMCrawfordIA Executed116.5 MW20192025
Hoodlebug Solar Energy Center
AF1-272
SolarPJMIndianaIA Executed110 MW20192027
Bradford Solar
AE2-139
SolarPJMMckeanIA Executed100.5 MW20192027
Queue AH2-405
AH2-405
SolarPJMFranklinFeasibility Study100 MW20222026
Queue AI1-101
AI1-101
SolarPJMLackawannaFeasibility Study100 MW20222029
Rockdale Solar
AF1-143
SolarPJMSomersetIA Executed100 MW20192028
Queue AI1-038
AI1-038
SolarPJMCarbonFeasibility Study95.8 MW20222024
Squab Solar
AE2-316
SolarPJMJeffersonIA Executed90 MW20192027
Queue AH2-115
AH2-115
SolarPJMTiogaFeasibility Study85 MW20222026
Queue AH2-116
AH2-116
SolarPJMCambriaFeasibility Study85 MW20222026
MPG Solar
AE2-262
SolarPJMCentreIA Executed83.6 MW20192028
Queue AI2-063
AI2-063
SolarPJMMckeanFeasibility Study82.5 MW20232027
Beaver Creek Solarsusp.
AD2-062
SolarPJMFranklinIA Executed80.3 MW20182024
Queue AH2-158
AH2-158
SolarPJMSomersetFeasibility Study80 MW20222025
Swiftwater Solar
AE2-175
SolarPJMMonroeIA Executed80 MW20192025
Walker Solar Two
AF2-361
SolarPJMJuniataIA Executed80 MW20202026
Wilson Solar
AF1-098
SolarPJMErieIA Executed80 MW20192028
Strinestown Solar Projectsusp.
AE1-129
SolarPJMYorkIA Executed79.6 MW20182027
MPG Solar
AE2-263
SolarPJMCentreIA Executed78.4 MW20192028
Granite Hill Solarsusp.
AE2-345
SolarPJMAdamsIA Executed70 MW20192026
Queue AI2-195
AI2-195
SolarPJMLycomingFeasibility Study69.9 MW20232025
Julius Solar
AH1-460
SolarPJMSomersetSystem Impact Study66 MW20252024
Queue AH2-195
AH2-195
SolarPJMIndianaFeasibility Study65 MW20222027
Iris Energy LLC project
AG2-411
SolarPJMSomersetSystem Impact Study63 MW20252024
Queue AI1-105
AI1-105
SolarPJMLuzerneFeasibility Study60 MW20222026
Mora Solar
AG1-156
SolarPJMCarbonIA Executed60 MW20202027
Dover Solarsusp.
AE2-211
SolarPJMYorkIA Executed55 MW20192026
Queue AI2-196
AI2-196
SolarPJMLycomingFeasibility Study51.5 MW20232025
Queue AH2-135
AH2-135
SolarPJMLuzerneFeasibility Study50 MW20222025
MC Solar I
AE2-285
SolarPJMMercerIA Executed50 MW20192027
Maple Hill-Fiddlers 1 SP (Bear Rock)
AF2-050
SolarPJMCambriaSystem Impact Study50 MW20192021
Queue AF1-302
AF1-302
SolarPJMJeffersonIA Executed42 MW20192027
Queue AI2-475
AI2-475
SolarPJMMontourFeasibility Study40.6 MW20232026
Queue AH2-295
AH2-295
SolarPJMGreeneFeasibility Study40 MW20222025
Green Meadows Solar
AG1-054
SolarPJMLawrenceIA Executed40 MW20202027
Poseidon Solar 1
AH1-247
SolarPJMFayetteSystem Impact Study40 MW20252024
Plainfield Solar, LLC project
AG2-074
SolarPJMCarbonSystem Impact Study38 MW20252023
Queue AH2-129
AH2-129
SolarPJMArmstrongFeasibility Study36 MW20222026
Cottontail Solar 7susp.
AF1-226
SolarPJMColumbiaIA Executed35 MW20192028
Potter Solar
AE2-074
SolarPJMPotterIA Executed35 MW20192026
Queue AI2-474
AI2-474
SolarPJMMontourFeasibility Study34.8 MW20232026
Queue AI2-471
AI2-471
SolarPJMMontourFeasibility Study29.5 MW20232025
Queue AI2-473
AI2-473
SolarPJMMontourFeasibility Study29 MW20232026
Poseidon Solar 2
AH1-248
SolarPJMFayetteSystem Impact Study25 MW20252024
Queue AI2-154
AI2-154
SolarPJMCentreFeasibility Study24 MW20232025
Queue AI2-415
AI2-415
SolarPJMButlerFeasibility Study20.3 MW20232026
Harlansburg PV I, LLC project
AG2-236
SolarPJMLawrenceSystem Impact Study20 MW20252024
Robin Solar LLC project
AG2-356
SolarPJMBradfordSystem Impact Study20 MW20252023
Chestnut Solar LLC project
AG2-561
SolarPJMIndianaSystem Impact Study20 MW20252023
Queue AH2-063
AH2-063
SolarPJMBeaverFeasibility Study20 MW20212023
Queue AH2-187
AH2-187
SolarPJMClarionFeasibility Study20 MW20222025
BL-Hileman Hollow
AG1-281
SolarPJMBlairIA Executed20 MW20202027
Black Moshannon Solar
AG1-377
SolarPJMCentreIA Executed20 MW20202023
Black Moshannon Solar
AG1-378
SolarPJMCentreIA Executed20 MW20202023
CL- Belsena Solar
AF2-296
SolarPJMClearfieldIA Executed20 MW20202028
CL-Green Acres
AF1-134
SolarPJMClearfieldIA Executed20 MW20192028
Club Ford Energy Center
AF2-421
SolarPJMAdamsIA Executed20 MW20202028
Club Ford Energy Center
AG1-164
SolarPJMLuzerneIA Executed20 MW20202027
Club Ford Energy Center
AG1-165
SolarPJMLuzerneIA Executed20 MW20202027
Confer Solar Isusp.
AE2-001
SolarPJMCentreIA Executed20 MW20182026
Dover Solarsusp.
AF1-057
SolarPJMYorkIA Executed20 MW20192026
FR-Williamsport
AF1-254
SolarPJMFranklinIA Executed20 MW20192025
Farmers Valley Solar
AF2-238
SolarPJMBradfordIA Executed20 MW20202028
Franklin Solar
AF1-094
SolarPJMCrawfordIA Executed20 MW20192026
Frosty Valley Energy Center
AF2-433
SolarPJMColumbiaIA Executed20 MW20202027
Gobbler Knob
AF2-229
SolarPJMCumberlandIA Executed20 MW20202027
HU-Loggingsusp.
AE2-118
SolarPJMHuntingdonIA Executed20 MW20192024
HU-Paulssusp.
AE2-117
SolarPJMHuntingdonIA Executed20 MW20192027
Henry Solar
AG1-100
SolarPJMCrawfordIA Executed20 MW20202027
Jackson Center Solar Facility
AE1-183
SolarPJMMercerIA Executed20 MW20182026
Jackson Center Solar II
AF1-093
SolarPJMMercerIA Executed20 MW20192026
Jakes Hollow Solarsusp.
AF1-153
SolarPJMElkIA Executed20 MW20192027
Limestone Solar
AF1-333
SolarPJMUnionIA Executed20 MW20192027
Limestone Solar
AF1-337
SolarPJMUnionIA Executed20 MW20192027
Limestone Solar
AF1-338
SolarPJMUnionIA Executed20 MW20192027
Limestone Solar
AF1-339
SolarPJMUnionIA Executed20 MW20192027
Montour 1susp.
AE2-110
SolarPJMColumbiaIA Executed20 MW20192025
Mountain Hollysusp.
AE2-241
SolarPJMColumbiaIA Executed20 MW20192027
Nichols Solar
AG1-040
SolarPJMCrawfordIA Executed20 MW20202026
Shamrock Energy Center
AF2-424
SolarPJMNorthumberlandIA Executed20 MW20202027
Shamrock Energy Center
AF2-425
SolarPJMAdamsIA Executed20 MW20202027
SunEast Hooversville Solarsusp.
AF1-321
SolarPJMSomersetIA Executed20 MW20192026
SunEast Hooversville Solarsusp.
AF2-001
SolarPJMSomersetIA Executed20 MW20192026
UN-Kylertown
AE2-131
SolarPJMWestmorelandIA Executed20 MW20192027
WA-Cochecton 2
AF2-417
SolarPJMAdamsIA Executed20 MW20202027
Queue AI1-143
AI1-143
SolarPJMArmstrongFeasibility Study19.9 MW20222025
McVille Solar
AH1-452
SolarPJMArmstrongSystem Impact Study19.9 MW20252023
Queue AH2-163
AH2-163
SolarPJMArmstrongFeasibility Study19.8 MW20222026
Queue AI1-076
AI1-076
SolarPJMDelawareFeasibility Study19.8 MW20222024
Norwegian Solarsusp.
AF2-445A
SolarPJMNorthumberlandIA Executed19.8 MW20202024
Stoneybrook Solar
AF2-086
SolarPJMColumbiaIA Executed19.6 MW20202027
CL-Shiloh LLC project
AH1-667
SolarPJMClearfieldSystem Impact Study18 MW2025

Showing the 100 largest of 164 projects by requested capacity.

Browse Pennsylvania's full interconnection queue. Compare with operating capacity: 62 operating solar plants in Pennsylvania. Nationwide: Solar plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).