Pennsylvania · Solar
Proposed solar projects in Pennsylvania
There are 88 proposed solar projects in Pennsylvania's interconnection queue, totaling 4.36 GW of requested capacity. The largest is Mineral Basin Solar Power at 401.6 MW, and the median planned online year is 2027.
88
Proposed projects
4.36 GW
Requested capacity
49.5 MW
Average project size
2027
Median planned online year
All proposed solar projects in Pennsylvania
| Type | ||||
|---|---|---|---|---|
| Mineral Basin Solar Power 1080 | Solar | 401.6 MW | 2020 | 2029 |
| Moonlight Flats Solar C24-301 | Solar | 250 MW | 2024 | 2029 |
| Cornerstone Solar AH1-545 | Solar | 200 MW | 2025 | 2025 |
| Kimberlite Solar C24-300 | Solar | 175 MW | 2024 | 2029 |
| MPG Solar AE2-263 | Solar | 162 MW | 2019 | 2028 |
| Trestle Solar Farm, LLC project AG2-176 | Solar | 150 MW | 2025 | 2024 |
| Queue AF1-302 AF1-302 | Solar | 132 MW | 2019 | 2027 |
| Ridgeway Solar AE2-113 | Solar | 120 MW | 2019 | 2026 |
| Hoodlebug Solar Energy Center AF1-272 | Solar | 110 MW | 2019 | 2027 |
| Bradford Solar AE2-139 | Solar | 100.5 MW | 2019 | 2027 |
| Rockdale Solar AF1-143 | Solar | 100 MW | 2019 | 2028 |
| Squab Solar AE2-316 | Solar | 90 MW | 2019 | 2027 |
| MPG Solar AE2-262 | Solar | 83.6 MW | 2019 | 2028 |
| Limestone Solar AF1-339 | Solar | 80 MW | 2019 | 2027 |
| Swiftwater Solar AE2-175 | Solar | 80 MW | 2019 | 2025 |
| Walker Solar Two AF2-361 | Solar | 80 MW | 2020 | 2026 |
| Wilson Solarsusp. AF1-098 | Solar | 80 MW | 2019 | 2028 |
| Strinestown Solar Projectsusp. AE1-129 | Solar | 79.6 MW | 2018 | 2027 |
| Dover Solar AF1-057 | Solar | 75 MW | 2019 | 2027 |
| Granite Hill Solarsusp. AE2-345 | Solar | 70 MW | 2019 | 2026 |
| Julius Solar AH1-460 | Solar | 66 MW | 2025 | 2024 |
| Iris Energy LLC project AG2-411 | Solar | 63 MW | 2025 | 2024 |
| Club Ford Energy Center AG1-165 | Solar | 60 MW | 2020 | 2028 |
| Limestone Solar AF1-338 | Solar | 60 MW | 2019 | 2027 |
| Mora Solar AG1-156 | Solar | 60 MW | 2020 | 2028 |
| Dover Solar AE2-211 | Solar | 55 MW | 2019 | 2027 |
| MC Solar I AE2-285 | Solar | 50 MW | 2019 | 2027 |
| Maple Hill-Fiddlers 1 SP (Bear Rock) AF2-050 | Solar | 50 MW | 2019 | 2021 |
| SunEast Hooversville Solarsusp. AF2-002 | Solar | 50 MW | 2019 | 2026 |
| Club Ford Energy Center AG1-164 | Solar | 40 MW | 2020 | 2028 |
| Green Meadows Solar AG1-054 | Solar | 40 MW | 2020 | 2027 |
| Limestone Solar AF1-337 | Solar | 40 MW | 2019 | 2027 |
| Poseidon Solar 1 AH1-247 | Solar | 40 MW | 2025 | 2024 |
| Shamrock Energy Center AF2-425 | Solar | 40 MW | 2020 | 2027 |
| SunEast Hooversville Solarsusp. AF2-001 | Solar | 40 MW | 2019 | 2026 |
| Plainfield Solar, LLC project AG2-074 | Solar | 38 MW | 2025 | 2023 |
| Cottontail Solar 7susp. AF1-226 | Solar | 35 MW | 2019 | 2028 |
| Potter Solar AE2-074 | Solar | 35 MW | 2019 | 2026 |
| Poseidon Solar 2 AH1-248 | Solar | 25 MW | 2025 | 2024 |
| Harlansburg PV I, LLC project AG2-236 | Solar | 20 MW | 2025 | 2024 |
| Robin Solar LLC project AG2-356 | Solar | 20 MW | 2025 | 2023 |
| Chestnut Solar LLC project AG2-561 | Solar | 20 MW | 2025 | 2023 |
| Queue AF2-088 AF2-088 | Solar | 20 MW | 2020 | 2026 |
| BL-Hileman Hollow AG1-281 | Solar | 20 MW | 2020 | 2027 |
| Black Moshannon Solar AG1-377 | Solar | 20 MW | 2020 | 2023 |
| Black Moshannon Solar AG1-378 | Solar | 20 MW | 2020 | 2023 |
| CL- Belsena Solar AF2-296 | Solar | 20 MW | 2020 | 2028 |
| CL-Green Acres AF1-134 | Solar | 20 MW | 2019 | 2027 |
| Club Ford Energy Center AF2-421 | Solar | 20 MW | 2020 | 2028 |
| Confer Solar Isusp. AE2-001 | Solar | 20 MW | 2018 | 2026 |
| Farmers Valley Solar AF2-238 | Solar | 20 MW | 2020 | 2028 |
| Franklin Solar AF1-094 | Solar | 20 MW | 2019 | 2026 |
| Frosty Valley Energy Center AF2-433 | Solar | 20 MW | 2020 | 2028 |
| Gobbler Knob AF2-229 | Solar | 20 MW | 2020 | 2028 |
| HU-Logging AE2-118 | Solar | 20 MW | 2019 | 2027 |
| HU-Paulssusp. AE2-117 | Solar | 20 MW | 2019 | 2027 |
| Henry Solar AG1-100 | Solar | 20 MW | 2020 | 2027 |
| Jackson Center Solar Facility AE1-183 | Solar | 20 MW | 2018 | 2026 |
| Jackson Center Solar II AF1-093 | Solar | 20 MW | 2019 | 2026 |
| Jakes Hollow Solarsusp. AF1-153 | Solar | 20 MW | 2019 | 2027 |
| Limestone Solar AF1-333 | Solar | 20 MW | 2019 | 2027 |
| Montour 1susp. AE2-110 | Solar | 20 MW | 2019 | 2025 |
| Mountain Hollysusp. AE2-241 | Solar | 20 MW | 2019 | 2027 |
| Nichols Solar AG1-040 | Solar | 20 MW | 2020 | 2027 |
| Shamrock Energy Center AF2-424 | Solar | 20 MW | 2020 | 2027 |
| SunEast Hooversville Solarsusp. AF1-321 | Solar | 20 MW | 2019 | 2026 |
| UN-Kylertown AE2-131 | Solar | 20 MW | 2019 | 2027 |
| WA-Cochecton 2 AF2-417 | Solar | 20 MW | 2020 | 2028 |
| McVille Solar AH1-452 | Solar | 19.9 MW | 2025 | 2023 |
| Stoneybrook Solar AF2-086 | Solar | 19.6 MW | 2020 | 2028 |
| CL-Shiloh LLC project AH1-667 | Solar | 18 MW | 2025 | — |
| Queue AF2-294susp. AF2-294 | Solar | 17 MW | 2020 | 2025 |
| Sugaree Solar LLC project AG2-200 | Solar | 17 MW | 2025 | 2023 |
| G Morris Solarsusp. AF1-271A | Solar | 17 MW | 2019 | 2026 |
| BL-Diamond Bear Rocks AF1-140 | Solar | 16.3 MW | 2019 | 2026 |
| CE-FILMOREsusp. AE2-248 | Solar | 16 MW | 2019 | 2027 |
| Boyles Run Solar AG1-259 | Solar | 15.9 MW | 2020 | 2028 |
| Boyles Run Solar AG1-260 | Solar | 15.9 MW | 2020 | 2028 |
| FU-Hanks Solar AF1-136 | Solar | 15.7 MW | 2019 | 2027 |
| Morgan Street-Cochranton 34.5 kVsusp. AG1-197 | Solar | 15 MW | 2020 | 2026 |
| Stony Creek Solarsusp. AF2-221 | Solar | 15 MW | 2020 | 2025 |
| Queue AF2-039 AF2-039 | Solar | 13.5 MW | 2019 | 2026 |
| CL-Route 58 Bsusp. AF1-167 | Solar | 13.5 MW | 2019 | 2026 |
| Costen Solar, Inc project AG2-166 | Solar | 10 MW | 2025 | 2023 |
| PG Solar LLC project AG2-037 | Solar | 4.7 MW | 2025 | 2021 |
| Greenfield CSG 1susp. AG1-253 | Solar | 4 MW | 2020 | 2025 |
| Springfield CSG 1susp. AG1-251 | Solar | 3.9 MW | 2020 | 2024 |
| Great Lake Growerssusp. AG1-140 | Solar | 2.6 MW | 2020 | 2024 |
Browse Pennsylvania's full interconnection queue. Compare with operating capacity: 62 operating solar plants in Pennsylvania. Nationwide: Solar plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition). Data: LBNL backbone through December 31, 2025; ISO-region statuses refreshed monthly (last: July 2026); non-ISO West and Southeast as of the LBNL edition.