Wyoming · Battery

Proposed battery projects in Wyoming

There are 5 proposed battery projects in Wyoming's interconnection queue, totaling 929 MW of requested capacity. The largest is Queue S0026 at 350 MW, and the median planned online year is 2026.

5
Proposed projects
929 MW
Requested capacity
185.8 MW
Average project size
2026
Median planned online year

All proposed battery projects in Wyoming

TypeRegionIA Status
Queue S0026
S0026
BatteryWestConverseIn Progress (unknown study)350 MW20242026
Queue S0028
S0028
BatteryWestConverseIn Progress (unknown study)320 MW20242026
Queue S0025
S0025
BatteryWestNatronaIn Progress (unknown study)100 MW20242026
Queue S0038
S0038
BatteryWestConverseIn Progress (unknown study)80 MW20252028
Queue 2008-03-01 00:00:00
2008-03-01 00:00:00
BatteryWestLaramieCluster Study79 MW20252028

Browse Wyoming's full interconnection queue. Nationwide: Storage plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).