Armenia Mountain Wind Farm

A 100.5 MW wind power plant in Tioga, Pennsylvania, owned by ALLETE Clean Energy, commissioned in 2009.

Facility nameplate · EIA Plant ID 57044Wind
Nameplate capacity
100.5 MW
Primary fuel
Wind
Commissioned
2009
Time in queue (20062009)
3.9 yrs
Owner
ALLETE Clean Energy
Location
Generation (2024)
235.4 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1

This facility was matched to a PJM Interconnection interconnection request (LBNL Queued Up): queued 2006, commercial operation 2009 3.9 years in the queue. See the PJM queue or typical durations.

Reported annual generation

YearGWh
2015261.2
2016262.4
2017267.5
2018263.6
2019232.6
2020262.2
2021236.6
2022266.6
2023224
2024235.4

Nearby power plants

PlantFuelCapacityDistance
AlpacaNatural Gas21 MW~12 km
Beaver Dam (PA)Natural Gas22 MW~17 km
Norther Tier LandfillWaste1.6 MW~19 km
BlossburgNatural Gas24 MW~20 km
MilanNatural Gas21 MW~27 km
Laurel Hill WindWind69 MW~29 km

See all wind plants in Pennsylvania or browse all plants in Pennsylvania.