Interconnection region
PJM Interconnection queue
698 proposed projects — 612 active and 86 suspended — are in the PJM Interconnection queue, totaling 88.17 GW of requested capacity. Projects that reached commercial operation here took a median of 3.2 years from interconnection request to online date (1,180 completed projects).
698
Proposed projects
88.17 GW
Requested capacity
Solar
Largest resource type
3.2 yrs
Median request → operation
Requested capacity by resource type
Solar 53.0%Gas 14.4%Battery 13.3%Wind 7.0%Solar + Battery 5.8%Offshore Wind 4.5%Nuclear 1.8%Hydro 0.1%
By state in PJM Interconnection
Largest proposed projects in PJM Interconnection
| Type | ||||
|---|---|---|---|---|
| CPV Shay, LLC project AG2-582 | Gas | 2.10 GW | 2025 | 2026 |
| Chestnut Run Energy LLC project AH1-680 | Gas | 1.30 GW | 2025 | — |
| Maidsville CCGT AE1-105 | Gas | 1.27 GW | 2018 | 2031 |
| Constellation Energy Generation, LLC project AH1-695 | Nuclear | 859 MW | 2025 | — |
| Heritage Prairie Wind AD1-100 | Wind | 850 MW | 2017 | 2028 |
| CVOW 2, OSS 2 – T2G07 AF1-124 | Offshore Wind | 836 MW | 2019 | 2032 |
| CVOW 1, OSS 1 - T1L11 AF1-123 | Offshore Wind | 833 MW | 2019 | 2032 |
| CVOW 3, OSS 3 – T3G15 AF1-125 | Offshore Wind | 820 MW | 2019 | 2032 |
| Ocean Windsusp. AE1-020 | Offshore Wind | 816 MW | 2018 | 2026 |
| Oak Run Solar Project AG1-126 | Solar | 800 MW | 2020 | 2030 |
| Blackwater Solar AE1-173 | Solar | 800 MW | 2018 | 2030 |
| East Kentucky Power Cooperative, Inc. project AH1-721 | Gas | 786 MW | 2025 | — |
| West Lorain Power Plant 345 kV AG1-500 | Gas | 784.6 MW | 2020 | 2031 |
| Tenaska Power Generation, LLC project AH1-712 | Gas | 776 MW | 2025 | — |
| Tenaska Power Generation, LLC project AH1-723 | Gas | 776 MW | 2025 | — |
| Bluegrass Power LLC project AG2-072 | Gas | 700 MW | 2025 | 2026 |
| Chalk Point Steam, LLC project AH1-552 | Solar + Battery | 670.2 MW | 2025 | 2025 |
| Cardinal Energy Storage East, LLC project AH1-716 | Battery | 650 MW | 2025 | — |
| Chesterfield CT Units 1 and 2 AF1-128 | Gas | 569 MW | 2019 | 2029 |
| Chesterfield CT Units 3&4 AF1-129 | Gas | 569 MW | 2019 | 2029 |
| Glen Falls Facility AA2-119 | Gas | 550 MW | 2015 | 2029 |
| Cardinal Energy Storage East, LLC project AH1-725 | Battery | 500 MW | 2025 | — |
| Fourth Quarter AG1-483 | Battery | 500 MW | 2020 | 2030 |
| Randolph Solar AF2-042 | Solar | 500 MW | 2019 | 2032 |
| Macadamia Solar AD1-076 | Solar | 484 MW | 2017 | 2028 |
| Sullivan Generating Station 1 AB1-087 | Gas | 480 MW | 2015 | 2028 |
| Sullivan Generating Station 2 AB1-088 | Gas | 480 MW | 2015 | 2028 |
| Dolphin Solar AG1-226 | Solar | 450 MW | 2020 | 2024 |
| Ocean Wind LLCsusp. AE1-104 | Offshore Wind | 432 MW | 2018 | 2026 |
| Cardinal Energy Storage East, LLC project AH1-727 | Battery | 425 MW | 2025 | — |
| Troy Energy, LLC project AH1-711 | Gas | 408.2 MW | 2025 | — |
| Monarch Grid, LLC project AG2-545 | Battery | 400 MW | 2025 | 2024 |
| Panther Grove 2 AE2-255 | Wind | 400 MW | 2019 | 2028 |
| Oak Run Solar Project AG1-125 | Solar | 400 MW | 2020 | 2030 |
| Zeus Energy, LLC project AG2-570 | Solar | 400 MW | 2025 | 2024 |
| Cassius Blue Solar AF1-069 | Solar + Battery | 394 MW | 2019 | 2031 |
| Macadamia Solar AD1-075 | Solar | 375 MW | 2017 | 2028 |
| Harvey Solar I AG1-034 | Solar | 362.5 MW | 2020 | 2029 |
| Panther Grove Wind AE1-163 | Wind | 350 MW | 2018 | 2027 |
| Monarch Solar, LLC project AG2-436 | Solar | 350 MW | 2025 | 2023 |
| Honeybee Solar, LLC AH1-528 | Solar | 300.8 MW | 2025 | 2025 |
| Mackinaw Solar LLC project AG2-363 | Solar | 300 MW | 2025 | 2024 |
| Burr Oak Solar AG1-118 | Solar | 300 MW | 2020 | 2023 |
| Dawson Solar AG1-374 | Solar | 300 MW | 2020 | 2024 |
| Heritage Prairie Solar AE2-152 | Solar | 300 MW | 2019 | 2027 |
| Panther Grove 2 AE1-113 | Wind | 300 MW | 2018 | 2028 |
| Pleasant Grove Solar AF2-349 | Solar | 300 MW | 2020 | 2023 |
| South Dixon Solar AF2-182 | Solar | 300 MW | 2020 | 2022 |
| Steward Creek Solar AF2-041 | Solar | 300 MW | 2019 | 2023 |
| Mammoth Central Energy Center AF2-132 | Solar | 300 MW | 2020 | 2027 |
Showing the 50 largest of 698 projects by requested capacity.
Browse the national queue or read the queue insights.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition). Statuses refreshed from PJM Interconnection queue data as of 2026-07-21; LBNL backbone through December 31, 2025.