Aviator Wind
A 525 MW wind power plant in Coke, Texas, owned by Aviator Wind, LLC, commissioned in 2021.
Facility nameplate · EIA Plant ID 63209Wind
Nameplate capacity
525 MW
Primary fuel
Wind
Commissioned
2021
Time in queue (2017→2021)
3.5 yrs
Owner
Aviator Wind, LLC
Location
Coke, Texas
Coordinates
Generation (2024)
1,785.5 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
This facility was matched to a ERCOT interconnection request (LBNL Queued Up): queued 2017, commercial operation 2021 — 3.5 years in the queue. See the ERCOT queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2021 | 1,793.1 | |
| 2022 | 1,894.9 | |
| 2023 | 1,823.5 | |
| 2024 | 1,785.5 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Bluebell Solar | Solar | 30 MW | ~15 km |
| Bluebell Solar II | Solar | 115 MW | ~16 km |
| Goat Wind LP | Wind | 149.6 MW | ~20 km |
| Jameson Gas Processing Plant | Natural Gas | 1.8 MW | ~29 km |
| Rambler | Solar | 200 MW | ~32 km |
| Capricorn Ridge Wind LLC | Wind | 662.5 MW | ~35 km |