Blue Harvest Solar Park

A 49.9 MW solar power plant in Putnam, Ohio, owned by Blue Harvest Solar Park LLC, commissioned in 2023.

Facility nameplate · EIA Plant ID 66249Solar
Nameplate capacity
49.9 MW
Primary fuel
Solar
Commissioned
2023
Time in queue (2017→2023)
6.2 yrs
Owner
Blue Harvest Solar Park LLC
Location
Putnam, Ohio
Generation (2024)
105.8 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a PJM Interconnection interconnection request (LBNL Queued Up): queued 2017, commercial operation 2023 — 6.2 years in the queue. See the PJM queue or typical durations.

Location

Map of the United States showing the location of Blue Harvest Solar Park

Putnam, Ohio · 41.0917, -84.2744

Reported annual generation

YearGWh
202324.7
2024105.8

Nearby power plants

PlantFuelCapacityDistance
Auglaize HydroHydroelectric3.6 MW~19 km
Whirlpool Corporation - Ottawa Wind FarmWind1.5 MW~22 km
Richland (OH)Natural Gas450 MW~24 km
POET Biorefining - Leipsic, LLCNatural Gas3.5 MW~26 km
Haviland Plastic ProductsWind4.5 MW~28 km
Northwest Ohio WindWind109.8 MW~28 km

See all solar plants in Ohio or browse all plants in Ohio.